HomeMy WebLinkAboutReso 28-19 Coast Guard CUPRESOLUTION NO. 28-19
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MORRO BAY, CALIFORNIA
APPROVING THE CONCEPT /PRECISE PLAN FOR CONDITIONAL USE PERMIT (CUP 18-
10) FOR 806SF ADDITION TO US COAST GUARD STATION BUILDING
AT 1279 EMBARCADERO, US COAST GUARD
(CITY LEASE SITE 141).
WHEREAS, the Planning Commission of the City of Morro Bay conducted a public hearing at
the Morro Bay Veteran's Hall, 209 Surf Street, Morro Bay, California, on April 16, 2019, for the
purpose of considering the Concept/Precise Plan for Conditional Use Permit #CUP18-10 and
adopted PC Resolution 07-19 to forward a favorable recommendation to the City Council for
approval; and
WHEREAS, the City Council conducted a public hearing at the Morro Bay Veteran's Hall, 209
Surf Street, Morro Bay, California, on May 14, 2019, pursuant to the Planned Development
regulations (Morro Bay Municipal Code (MBMC) section 17,40.030), for the purpose of
considering the Project for 1279 Embarcadero, also known as the US Coast Guard Station
Building, in an area within the original jurisdiction of the California Coastal Commission; and
WHEREAS, notices of said public hearing were made at the time and in the manner required by
law; and
WHEREAS, the City Council has duly considered all evidence, including the testimony of the
applicant, interested parties, and the evaluation and recommendations by staff, presented at
said Council public hearing.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Morro Bay as follows:
Section 1: Findings. Based upon all the evidence, the Council makes the following findings:
California Environmental Quality Act (CEQA)
A. That for purposes of the California Environmental Quality Act, Case No. CUP18-10 is
categorically exempt under Section 15301, Class 1 e. This exemption allows for additions to
existing structures if the increase is not more than 50 percent of floor area or 2,500 square
feet whichever is less, for which the proposed 806sf Coast Guard addition would qualify for
an exemption. In addition, none of the exceptions found in CEQA Section 15300.2 apply to
this project.
Conditional Use Permit Findings
A. The project will not be detrimental to the health, safety, morals, comfort and general welfare
of the persons residing or working in the neighborhood in that the 806sf addition to the
existing Coast Guard building at 1279 Embarcadero is a permitted use as a government
building within the commercial/recreational fishing zoning district; and said building addition
structure complies with all applicable project conditions and City regulations, is consistent
with the City's Local Coastal Program, and as a branch of the U.S. military is responsible for
maritime safety.
B. The project will not be injurious or detrimental to property and improvements in the
neighborhood and the general welfare of the City in that the proposed addition will provide
enhanced ability for the Coast Guard to fulfil its mission of boating safety, search and
rescue, and enforcement of maritime laws while also indirectly benefitting public safety and
recreation for visitors and residents and is consistent with the character of the existing
development. The loss of five parking spaces will not be detrimental to the lease site or
adjacent public parking lot because the addition is proposed to maintain the minimum drive
aisle width to allow for continued function of the parking lot.
C. The proposed project includes the removal of 5 parking spaces in the area where the
addition is located, and the City Council has adopted Resolution No. 22-19, approving a
Supplemental Lease Agreement with the Coast Guard requiring payment of $75,000
($15,000 per space) to offset the removal of the parking spaces.
Waterfront Master Plan Findings
A. The proposed project makes a positive contribution to the visual accessibility to the bay and
rock while supporting the harbor.
B. In the case of granting exceptions to development standards including lot coverage, the
proposed project provides significant public benefit pursuant to the Planned Development
Overlay zone requirements in that the proposed project of an 806sf single story addition to
an existing Coast Guard building provides for and supports and actively encourages the
continued permanent presence by the Coast Guard as an essential element of boating
safety in the region.
C. Meets the Waterfront plan height limit, bulk, and scale requirements in that the proposed
project does not exceed the maximum height allowed and interesting articulation breaks up
the bulk and scale.
D. The project does not worsen or block more views, it does not block view corridors or intrude
into pedestrian access areas. It takes advantage of outward views and characteristics of the
topography in that the project proposes a single story addition on the east side of the
building outside of public view corridors.
E. The proposed project provides the amenities identified in the Waterfront Master Plan,
facilitates visual and physical access to the waterfront, and takes advantage of outward
views and characteristics of the topography.
F. The proposed project makes a positive contribution to the working fishing village character
and quality of the Embarcadero area in that the new project supports and actively
encourages the continued permanent presence by the Coast Guard as an essential element
of boating safety in the region..
G. The proposed project recognizes the pedestrian orientation of the Embarcadero by
maintaining the surrounding area and proposing a small addition with minimal impact to the
surrounding parking lot that does not create view impacts and also in that the project will
provide historical interpretive sign on the history of the US Coast Guard for pedestrian
passers-by as a public educational benefit that is consistent with the character of the
existing development.
H. The project gives its occupants and the public some variety in materials and/or application in
that the project is designed to match color and materials of existing building and retain
building character.
The project contains the elements of harmony, continuity, proportion, simplicity, and balance,
and its appearance matches its function and the uses proposed.
J. The proposed project does not diminish, either directly or by cumulative impact of several
similar projects, the use, enjoyment, or attractiveness of adjacent buildings and provides a
visual and pedestrian transition to its immediate neighbor.
Architectural Consideration
A. As required by Ordinance Section 17.48.200 the Planning Commission finds that the
architectural treatment and general appearance of all proposed structures and open
areas are in keeping with the character of the surrounding areas, are compatible with
any design themes adopted by the city, and are not detrimental to the orderly and
harmonious development; of the city or to the desirability of investment of occupation in
the area.
Section 2. Action. The City Council does hereby approve Concept/Precise Plan Conditional Use
Permit #CUP18-10 subject to the following conditions:
STANDARD CONDITIONS
1. This permit is granted for the Coast Guard addition on land described in the City Council
staff report dated May 1, 2019, (Council meeting date May 14, 2019) for the project at
1279 Embarcadero depicted on plans dated March 19, 2019, on file with the Community
Development Department, as modified by these conditions of approval, and more
specifically described as follows: Site development, including all buildings and other
features, shall be located and designed substantially as shown on Planning Commission
approved plans submitted for CUP18-10, unless otherwise specified herein.
2. Inaugurate Within Two Years: Unless the construction or operation of the structure,
facility, or use is commenced not later than two (2) years after the effective date of this
Resolution and is diligently pursued, thereafter, this approval will automatically become
null and void; provided, however, that upon the written request of the applicant, prior to
the expiration of this approval, the applicant may request up to two extensions for not
more than one (1) additional year each. Any extension may be granted by the City's
Community Development Director, upon finding the project complies with all applicable
provisions of the Morro Bay Municipal Code (the "MBMC"), General Plan and certified
Local Coastal Program Land Use Plan (LCP) in effect at the time of the extension
request.
3. Changes: Minor changes to the project description and/or conditions of approval shall
be subject to review and approval by the Community Development Director. Any
changes to this approved permit determined, by the Director, not to be minor shall
require the filing of an application for a permit amendment subject to Planning
Commission review.
4. Compliance with the Law: (a) All requirements of any law, ordinance or regulation %J the
State of California, the City, and any other governmental entity shall be complied with in
the exercise of this approval, (b) This project shall meet all applicable requirements
under the MBMC, and shall be consistent with all programs and policies contained in the
LCP and General Plan for the City.
5. Hold Harmless: The applicant, as a condition of approval, hereby agrees to defend,
indemnify, and hold harmless the City, its agents, officers, and employees, from any
claim, action, or proceeding against the City as a result of the action or inaction by the
City, or from any claim to attack, set aside, void, or annul this approval by the City of the
applicant's project; or applicants failure to comply with conditions of approval. Applicant
understands and acknowledges the City is under no obligation to defend any legal
actions challenging the City's actions with respect to the project. This condition and
agreement shall be binding on all successors and assigns.
6. Compliance with Conditions: The applicant's establishment of the use or development of
the subject property constitutes acknowledgement and acceptance of all Conditions of
Approval. Compliance with and execution of all conditions listed hereon shall be
required prior to obtaining final building inspection clearance. Deviation from this
requirement shall be permitted only by written consent of the Director or as authorized
by the Planning Commission. Failure to comply with any of these conditions shall render
this entitlement, at the discretion of the Director, null and void. Continuation of the use
without a valid entitlement will constitute a violation of the MBMC and is a misdemeanor.
7. Compliance with Morro Bay Standards: This project shall meet all applicable
requirements under the MBMC, and shall be consistent with all programs and policies
contained in the LCP and General Plan of the City.
8. Conditions of Approval: The Findings and Conditions of Approval shall be included as a
full-size sheet in the Building Plans.
BUILDING DIVISION CONDITIONS:
CONDITIONS TO BE MET PRIOR TO ISSUANCE OF A BUILDING PERMIT
1. Building permit plans shall be submitted by a California licensed architect or engineer
when required by the Business &Professions Code, except when otherwise approved
by the Chief Building Official,
2. The owner shall designate on the building permit application a registered design
professional who shall act as the Registered Design Professional in Responsible
Charge. The Registered Design Professional in Responsible Charge shall be
responsible for reviewing and coordinating submittal documents prepared by others
including phased and staggered submittal items, for compatibility with design of the
building.
3. The owner shall comply with the City's Structural Observation Program. The owner shall
employ the engineer or architect responsible for the structural design, or another
engineer or architect designated by the engineer of record or architect responsible for
the structural design, to perform structural observation as defined in Section 220.
Observed deficiencies shall be reported in writing to the owner's representative, special
inspector, contractor and the building official. The structural observer shall submit to the
building official a written statement that the site visits have been made and identify any
reported deficiencies that, to the best of the structural observer's knowledge, have not
been resolved.
4. The owner shall comply with the City's Special Inspection Program. Special inspections
will be required by Section 1704 of the California Building Code. All Special Inspectors
shall first be approved by the Building Official to work in the jurisdiction. All field reports
shall be provided to the City Building Inspector when requested at specified increments
in order for the construction to proceed. All final reports from Special Inspectors shall be
provided to the Building Official when they are complete and prior to final inspection.
5. Mitigation measures for natural occurring asbestos require approval from San Luis
Obispo County Air Pollution Control District,
6. A soils investigation performed by a
project. All cut and fill slopes shall be
for stability; details shall be provided.
Bay soils report waiver request.
qualified professional .shall be required for this
provided with subsurface drainage as necessary
Alternatively, submit a completed City of Morro
7. BUILDING PERMIT APPLICATION. To apply for building permits, submit three (3) sets
of construction plans to the Building Division,
8. The Title sheet of the plans shall include:
a. Street address, lot, block, track and Assessor Parcel Number.
b. Description of use.
C. Type of construction.
d. Maximum Height of the building allowed and proposed.
e. Floor area of the building(s).
f. Vicinity map.
g. Minimum building set back per zoning designation or conditional use approval.
9. All construction will conform to the 2016 California Building Code (CBC), 2016 California
Residential Code (CRC), 2016 California Fire Code (IFC), 2016 California Mechanical
Code (CMC), 2016 California Plumbing Code (CPC), 2016 California Electrical Code
(CEC), 2016 California Energy Code, 2016 California Green Code (CGBC), and
Accessibility Standards where applicable and all City codes as they apply to this project.
(Code adoption dates are subject to change. The code adoption year is established by
application date of plans submitted to the Building Division for plan review.)
CONDITIONS TO BE MET DURING CONSTRUCTION
10. SITE MAINTENANCE. During construction, the site shall be maintained so as to not
infringe on neighboring property, such as debris and dust.
11. ARCHAEOLOGICAL MATERIALS. In the event unforeseen archaeological resources
are unearthed during any construction activities, all grading and or excavation shall
cease in the immediate area and the find left untouched. The Building Official shall be
notified so that the extent and location of discovered materials may be recorded by a
qualified archaeologist, Native American, or paleontologist, whichever is appropriate.
The qualified professional shall evaluate the find and make reservations related to the
preservation or disposition of artifacts in accordance with applicable laws and
ordinances. If discovered archaeological resources are found to include human
remains, or in any other case when human remains are discovered during construction,
the Building Official shall notify to county coroner. If human remains are found to be of
ancient age and of archaeological and spiritual significance, the Building Official shall
notify the Native American Heritage Commission. The developer shall be liable for costs
associated with the professional investigation.
12. A licensed surveyor or engineer shall verify pad elevations, setbacks, prior to foundation
inspection, and/or building height prior to framing inspection when determined necessary
by the Planning Division,
CONDITIONS TO BE MET PRIOR TO FINAL INSPECTION AND ISSUANCE OF
CERTIFICATE OF OCCUPANCY:
13. Prior to building division final approval all required inspections from the other various
divisions must have been completed and verified by a city inspector. All required final
inspection approvals must be obtained from the various departments and documented
on the permit card.
14. Title 24 form(s) 2F-6R (Certificate of installation) for building, mechanical, electrical and
plumbing systems.
FIRE DEPARTMENT CONDITIONS:
1. Automatic fire sprinklers. An automatic fire sprinkler system, in accordance with NFPA
13-D7 California Fire Code (Section 903) and Morro Bay Municipal Code (Section
14.08.090).
2. Fire Safety during Construction and Demolition shall be in accordance with 2016
California Fire Code, Chapter 33. This chapter prescribes minimum safeguards for
construction, alteration and demolition operations to provide reasonable safety to life and
property from fire during such operations.
3. Fire Apparatus Access Roads -Dimensions. Fire apparatus access roads shall have an
unobstructed width of not less than 20 feet, exclusive of shoulders, except for approved
security gates in accordance with Section 503.6, and an unobstructed vertical clearance
of not less than 13 feet 6 inches. (CFC 50362,1)
4. Fire Department access to equipment. Rooms or areas containing controls for Electrical,
FAU, Alarm and Fire Sprinkler Systems shall be identified by approved and appropriate
signage for Fire Department use. (CFC 1001.8)
PUBLIC WORKS CONDITIONS:
The following Public Works conditions shall be satisfied with the Building Plan submittal:
1. Stormwater Management: The City has adopted Low Impact Development (LID) and
Post Construction requirements to protect water quality and control runoff flow from new
and redevelopment projects. Projects with more than 2,500sf of new or redeveloped
impervious area are subject to these requirements. The submitted "SFR Performance
Requirement Determination Form" indicates this project is "Exempt".
2. Sewer Mainline: Indicate and label new sewer mainline per City specifications in the
"City of Morro Bay Standard Drawings and Specifications". Add note to "Maintain all
sewer lateral connections along sewer mainline".
3. Sewer Manhole: Indicate and label new sewer manhole per City standard detail S-3.
4. Sewer Lateral: Indicate and label new or existing sewer lateral and connections. If an
existing lateral is used, perform a video inspection of the lateral and submit to Public
Works via flash drive or DVD, prior to building permit plan approval. Lateral shall be
repaired as necessary and all repairs shall be noted on approved set of plans.
5. Sewer Backwater Valve: Indicate and label sewer backwater valve on plan. A sewer
backwater valve shall be installed on site to prevent a blockage or maintenance of the
municipal sewer main from causing damage to the proposed project (MBMC 14,24.070),
6. Erosion and Sediment Control Plan: For small projects less than one acre and less than
15% slope, provide a standard erosion and sediment control plan. Show on plans the
control measures to provide protection against erosion of adjacent property and prevent
sediment or debris from entering the City right of way, adjacent properties, any harbor,
waterway, or ecologically sensitive area.
7. Water Meter: Indicate and label new or existing water meter on plans.
8. Water Backflow Prevention Device: Verify and label all new or existing water backflow
preventers. Devices are required for fire water systems, irrigation systems on a
dedicated water meter, systems which may change in character of use (commercial
rentals, etc.), gray water systems, or any plumbing system which has cross -connections
or the ability to allow water of deteriorated sanitary quality to enter the public water
supply. Add note to plan that device is an approved domestic water backflow prevention
device.
9. Grading and Drainage: Indicate on plans the existing and updated contours, drainage
patterns, spot elevations, finish floor elevation and all existing and proposed drainage
pipes and structures.
Add the following Notes to the Plans:
Any damage, as a result of construction operations for this project, to City facilities, i.e.
curb/berm, street, sewer line, water line, or any public improvements shall be repaired at
no cost to the City of Morro Bay.
No work shall occur within (or use of) the City's Right of Way without an encroachment
permit. Encroachment permits are available at the City of Morro Bay Public Works
Office located at 955 Shasta Ave. The Encroachment permit shall be issued concurrently
with the building permit.
HARBOR CONDITIONS:
1. Applicant shall submit for a lease line amendment to be approved by the City Council
prior to issuance of a building permit.
PLANNING CONDITIONS:
1. Inspection: The applicant shall comply with all City conditions of approval and conditions
imposed by the California Coastal Commission and obtain final inspection clearance
from the Planning Division at the necessary time in order to ensure all conditions have
been met.
2. An interpretive sign with content relating to the historical nature of the Coast Guard in
Morro Bay shall be submitted for review and approval by the Community Development
Director for installation prior to final occupancy of the building permit.
3. Compliant ADA path of travel shall be shown on building construction plans.
Planning condition 4 added by the Planning Commission on 4/16/2019:
4. Applicant shall submit a construction staging and traffic control plan that minimizes
impact to neighboring business and pedestrian traffic to the greatest extent feasible.
Said plan shall be submitted for review and approval by the Community Development
Director prior to issuance of a building permit
PASSED AND ADOPTED by the Morro Bay City Council at a regular meeting thereof held on
this 14th day of May, 2019, on the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN
ATTEST
Headding, Addis, Davis, McPherson
None
Heller
None
ANA SWANSON, City Clerk