1 Daniel Ford No 00-GENERAL We are working on building the forms for the frog wall. We are
starting the form work approx. 200 feet from the front gate so
we will be able to extend the under ground pipe for the plant
tie in (at a later date)
We worked on the supports and handrail for the lift station.
a 4" check valve was installed in the lift station.
We fixed the frog fence on the east side of the job and fixed
the front fence.
2 Daniel Ford No 17-OUTDOOR STORAGE
AREA
We are continuing to bring material to this area and get it
ready to ship out.
3 Daniel Ford No SAFETY We continue to hold regular morning safety. We talked about
confined spaces and emphasized the benefits of good
stretching and proper housekeeping.
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
one slide gate was leaking a bit in the bnr so we will have to
drain it and figure out whats happening with the gate and
retest tomorrow
5 Daniel Ford No 95-OPERATIONS
BUILDING
Electra craft has installed all the lights and we laid out the tv
supports for the control room. we will have to do a small
modification to the mount for it to fit correctly
6 Daniel Ford No 96-MAINTENANCE
BUILDING
Kenects continues with the HVAC work we reminded them
(again) to remove all the blue tape off the floor. they said they
would take care of it, but that has not happened yet. they also
continue work on the HVAC units.
We are working on the floor repair for the concrete slab in this
area.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:18 AM PST
NOTES LOG
No.Created By Issue?Location Comments
Kenects has requested 2 more housekeeping pads and those
are being formed up.
7 Daniel Ford No 50-RO/UV BUILDING We drilled more holes and epoxied in anchors for some of the
pipe supports in this building
Electracraft continues to install electrical equipment in the
electrical room and Kenects is working on the plumbing for
this area.
8 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We were installing pipe supports for the PVC pipes in this area
today.
9 Daniel Ford No 20-HEADWORKS AREA We are installing the 16" elbow at the safe filter box.
The 6" WWS line at the fine screens is being worked on as well.
10 Daniel Ford No 90-CHEMICAL FACILITY We are taking down the shade structure we built for the
painters to do there fiberglassing.
11 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are doing misc patching and sacking in this area.
12 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We were installing chemical lines at the headworks and
excavating the 3" was line near the dewatering SOG.
MANPOWER LOG 53 Workers | 429.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 RARIG CONSTRUCTION, INC.4 7.5 30.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Steel
Created By: Daniel Ford
2 RARIG CONSTRUCTION, INC.4 7.5 30.0 17-OUTDOOR
STORAGE AREA
Notes:Siding
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:18 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
3 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Daniel Ford
4 RARIG CONSTRUCTION, INC.6 8.0 48.0 17-OUTDOOR
STORAGE AREA
Notes:Siding
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Carpenter Foreman
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Superintendent
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:Journeyman Laborers
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:Laborer Apprentice
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Journeyman operators
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:General Foreman
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:Journeyman Carpenters
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Laborer Foreman
Created By: Daniel Ford
13 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:Carpenters Apprentice
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:18 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
14 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:Journeyman Cement Mason
Created By: Daniel Ford
15 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:Apprentice Cement Mason
Created By: Daniel Ford
16 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:pipe fitter
Created By: Daniel Ford
17 ELECTRICRAFT, INC.9 8.0 72.0
Notes:Electrician
Created By: Rick Howland
18 Parada Painting Inc.2 10.0 20.0 90-CHEMICAL
FACILITY
Notes:grinding Fiberglass
Interior doors of the operations bldg
Created By: Monica Weiss
53 429.0
Manpower Log's Attachments:
17. ELECTRICRAFT, INC.
11-2-2021 Daily Report.xls
18. Parada Painting Inc.
2021.11.02 DFR.pdf
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:18 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:50AM Albertsons 882001444380 Snacks
Comments:Created By: Matt King
2 07:50AM Ryan Herco Flow Solutions 9788019 PVC Van Stone flange
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:18 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 07:50AM SMART & FINAL Snacks
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.02 Albertsons.pdf
2.
2021.11.02 Ryan Herco 24in VSF .pdf
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:18 AM PST
3.
2021.11.02 Smart Final.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
55°F 63°F 59°F 0.00 in.0.01 in.0.01 in.82%91%97%56°F 2.4 mph 5 mph 9 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
56°F
Partly Cloudy
58°F
Partly Cloudy
63°F
Partly Cloudy
63°F
Partly Cloudy
60°F
Partly Cloudy
59°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:55:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:18 AM PST