HomeMy WebLinkAbout2021-11-04FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 11/4/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We moved and organized material all over the site and were
clearing areas for paving..
Form work for the frog wall continues.
We continued installing rock and cleaning out the level
spreaders.
2 Daniel Ford No SAFETY We continue to hold regular morning safety. We talked about
confined spaces and emphasized the benefits of good
stretching and proper housekeeping.
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We are working on the FRP Baffle walls
12" 8" 6" SS pipes are being cut and fabricated for the BNR air
system
4 Daniel Ford No 95-OPERATIONS
BUILDING
misc layout, core drill for pipe supports for the monitor stand
5 Daniel Ford No 96-MAINTENANCE
BUILDING
We placed concrete in a few equipment pads for this area
6 Daniel Ford No 50-RO/UV BUILDING We drilled more holes and epoxied in anchors for some of the
pipe supports in this building
Electracraft continues to install electrical equipment in the
electrical room and Kenects is working on the plumbing for
this area.
7 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We were installing pipe supports for the PVC pipes in this area
today.
8 Daniel Ford No 20-HEADWORKS AREA We are installing the 16" elbow at the safe filter box.
The 6" WWS line at the fine screens is being worked on as well.
9 Daniel Ford No 90-CHEMICAL FACILITY We continued with the sacking of the exposed edge of the
slab.
The valve at the chemical building loading dock was installed
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 09:19 AM PST
NOTES LOG
No.Created By Issue?Location Comments
10 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
we are installing the RAS 14" flowmeters
11 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We finished working on the 3" WAS line near th dewatering.
The Chemical duct bank near the Calcite contactors was
finished
The 14" PRN line was exposed (4 hours)
We also exposed the 14" ROC line
12 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
We installed about 20 feet of pipe at the safe filter.
MANPOWER LOG 42 Workers | 346.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.9 8.0 72.0
Notes:Created By: Rick Howland
2 Parada Painting Inc.2 10.0 20.0 95-OPERATIONS
BUILDING
Notes:Doors 2nd coat
Created By: Monica Weiss
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Monica Weiss
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Monica Weiss
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 09:19 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Monica Weiss
7 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Monica Weiss
8 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Monica Weiss
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Monica Weiss
11 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhoofven
Created By: Monica Weiss
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 09:19 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
13 ELECTRICRAFT, INC.7 8.0 56.0
Notes:ELECTRICAL
Created By: Monica Weiss
14 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Monica Weiss
15 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Monica Weiss
16 Parada Painting Inc.2 8.0 16.0 90-CHEMICAL
FACILITY
Notes:Grinding Fiberglass
Created By: Monica Weiss
42 346.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
11-4-2021 Daily Report.xls
2. Parada Painting Inc.
2021.11.04 DFR.pdf
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 09:19 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:25AM Capital Flow 1258787 6in Bolt kits A31
Comments:Created By: Matt King
2 08:25AM Capital Flow 327609 10in Expansion Joint A60
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 09:19 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 08:25AM Confirm Biosciences S118693 Drug Tests
Comments:Created By: Matt King
4 08:25AM Jifco, Inc.Dismantling Joint Bolts and Rods A32
Comments:Created By: Matt King
5 08:25AM Miner's Ace Hardware 721644 Batteries, Blower, Wrench
Comments:Created By: Matt King
6 08:25AM HD Supply White Cap 44801854 Right Angle Attachment
Comments:Created By: Matt King
7 11:40AM CalPortland 1701817 A95 Pipe Encasement
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.04 Capflo 6in Bolt MR73_A31.pdf
2.
2021.11.04 Capflo 10in Exp Joint A60_MR103.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 09:19 AM PST
3.
2021.11.04 Confirm Drug Tests.pdf
4.
2021.11.04 JIFCO 36ML-1_A32 MR98.pdf
5.
2021.11.04 Miners Tools 721644.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 09:19 AM PST
6.
2021.11.04 White Cap 44801854 Tool Angle.pdf
7.
2021.11.04 Calportland 1701817 Pipe Encase A95.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 61°F 58°F 0.00 in.0.00 in.0.00 in.77%89%100%55°F 3.6 mph 11 mph 15 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
54°F
Clear
55°F
Clear
61°F
Partly Cloudy
61°F
Cloudy
61°F
Cloudy
60°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:40:00 AM No
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 09:19 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 9 of 9 Printed on 1/24/2023 at 09:19 AM PST