HomeMy WebLinkAbout2021-11-05FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 11/5/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We are working on building one side of the forms for the frog
wall.
We worked on the supports and handrail for the lift station.
a 4" check valve was installed in the lift station.
2 Daniel Ford No SAFETY We continue to hold regular morning safety. We talked about
confined spaces and emphasized the benefits of good
stretching and proper housekeeping.
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We were working on the SHT mixers and grinding on the top
of wall.
We aso cut Stubs for the SHT BV
We are welding the BNR air manifold. Also the 12" air manifold
and the 30" riser at the cassette tak are being installed.
4 Daniel Ford No 95-OPERATIONS
BUILDING
Electra craft has installed all the lights and we laid out the tv
supports for the control room. we will have to do a small
modification to the mount for it to fit correctly
5 Daniel Ford No 96-MAINTENANCE
BUILDING
We formed 2 equipment pads.
And the Overhead door company came and put the correct
motors on the overhead doors.
6 Daniel Ford No 50-RO/UV BUILDING We drilled more holes and epoxied in anchors for some of the
pipe supports in this building
Electracraft continues to install electrical equipment in the
electrical room and Kenects is working on the plumbing for
this area.
7 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We were installing pipe supports for the PVC pipes in this area
today.
8 Daniel Ford No 20-HEADWORKS AREA We are installing the 16" elbow at the safe filter box.
The 6" WWS line at the fine screens is being worked on as well.
FBV Morro Bay Joint Venture Page 1 of 10 Printed on 1/24/2023 at 09:19 AM PST
NOTES LOG
No.Created By Issue?Location Comments
9 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area
and are sacking the exposed edge.
10 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
The *" SS air piping is being installed for the casette tank
11 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We finished working on the 3" WAS line near th dewatering.
The Chemical duct bank near the Calcite contactors was
finished
The 14" PRN line was exposed (4 hours)
We also exposed the 14" ROC line
12 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
We installed about 20 feet of pipe at the safe filter.
MANPOWER LOG 34 Workers | 278.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.10 8.0 80.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Monica Weiss
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Monica Weiss
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 2 of 10 Printed on 1/24/2023 at 09:19 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
5 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Monica Weiss
6 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Monica Weiss
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Monica Weiss
8 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Monica Weiss
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhoofven
Created By: Monica Weiss
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 3 of 10 Printed on 1/24/2023 at 09:19 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Monica Weiss
13 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Monica Weiss
14 Parada Painting Inc.2 8.0 16.0 95-OPERATIONS
BUILDING
Notes:Finish Coat Interior doors
Created By: Monica Weiss
34 278.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
11-5-2021 Daily Report.xls
14. Parada Painting Inc.
2021.11.05 DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 10 Printed on 1/24/2023 at 09:19 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:40AM AHERN RENTALS - SANTA
MARIA
24219212 Soquel Stake Truck
Comments:Created By: Matt King
2 11:40AM Capital Flow 11353 Gaskets MR73
Comments:Created By: Matt King
3 11:40AM Capital Flow 32200169194 Return of 20x14 90 Bend DI
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 5 of 10 Printed on 1/24/2023 at 09:19 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
4 11:40AM Capital Flow 32200169194 Return of 20x14 90 Bend DI
Comments:Created By: Matt King
5 11:40AM ECS Environmental Systems 5659 Missing Odor Control gaskets and
backing ring
Comments:Created By: Matt King
6 11:40AM FERGUSON ENTERPRISES LLC 9541325 Thread Tape Pipe seal
Comments:Created By: Matt King
7 11:40AM Mid-Coast Fire Protection,
Inc.
10901652 Fire Protection
Comments:Created By: Matt King
8 11:40AM Shore-Tek Inc.6531 Shoring
Comments:Created By: Matt King
9 11:40AM Shore-Tek Inc.6532 Test Plug
Comments:Created By: Matt King
10 11:40AM HD Supply White Cap 44817171 Safety
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.05 Ahern Soquell Stake Truck.pdf
FBV Morro Bay Joint Venture Page 6 of 10 Printed on 1/24/2023 at 09:19 AM PST
2.
2021.11.05 Capflo MR73 Gaskets.pdf
3.
2021.11.05 Capflo Return of 20x14.pdf
4.
2021.11.05 Capflo Reurn to STAR 20x14 90.pdf
FBV Morro Bay Joint Venture Page 7 of 10 Printed on 1/24/2023 at 09:19 AM PST
5.
2021.11.05 ECS Odor Control Shims and Parts A20.pdf
6.
2021.11.05 Ferguson 9541325 Thread Tape Pipe Seal.pdf
7.
2021.11.05 Mid Coast Fire Protection.pdf
FBV Morro Bay Joint Venture Page 8 of 10 Printed on 1/24/2023 at 09:19 AM PST
8.
2021.11.05 Shoetek 490 Shoring 6531.pdf
9.
2021.11.05 Shoretek 490 Test Plug 6532.pdf
10.
2021.11.05 White Cap 44817171 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
58°F 73°F 62°F 0.00 in.0.00 in.0.00 in.44%70%84%52°F 8.4 mph 12 mph 18 mph
FBV Morro Bay Joint Venture Page 9 of 10 Printed on 1/24/2023 at 09:19 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
62°F
Cloudy
61°F
Cloudy
70°F
Cloudy
61°F
Cloudy
60°F
Clear
58°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:50:00 AM No
By Date Copies To