Loading...
HomeMy WebLinkAbout2021-11-08FBV Morro Bay Joint Venture 2999 Oak Rd. #490 Walnut Creek , California 94597 Project: 471 - Morro Bay Water Reclamation Facility  Morro Bay , California 93442 Daily Log: Monday 11/8/2021  Daily Log Completed  The Daily Log was completed by Monica Weiss on Mon Dec 13, 2021 at 03:37pmPST.   NOTES LOG    No.Created By Issue?Location Comments   1 Daniel Ford No 00-GENERAL PSG came out and delivered rebar . they also installed the 200 + feet of frog wall we have one sided. They will be back tomorrow morning to finish the installation and add dobies Electra craft was running the main electricity all over the site today. We loaded up Simi truck with aluminum beams, bridge jacks, and pipe braces, 8 inch srs pipe and 4 in scheduled 40 pipe. all to either be returned or taken back to our yard in SD 2 Daniel Ford No SAFETY We held our all hands meeting this morning and talked about various site conditions and read the extension cord safety sheet to the group 3 Daniel Ford No 30-TREATMENT AREA>32- Treatment Area - MBR System We set the inch mixed liquor pipe on the east sid e of the MBR cassette tank today, 4 Daniel Ford No 95-OPERATIONS BUILDING Kenects was doing some water testing today Pristine was on site to fix any cracks and damage to the concrete floor. We walked this building together and identified the damage done by RK&G we will separate that out. 5 Daniel Ford No 96-MAINTENANCE BUILDING We cleaned this building. Kenects still has a lot of tape residue on the floors that will have to be det with before Pristine can do there work here. Parada went to get their mill testing machine tomorrow and we pointed out all the paint on the Electrical room floor, they have acknowledged, it and will deal with it. 6 Daniel Ford No 50-RO/UV BUILDING We drilled more holes and epoxied in anchors for some of the pipe supports in this building. we hit one conduit and didn't   FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:20 AM PST          NOTES LOG    No.Created By Issue?Location Comments   realize it until epoxy was put in the hole. We notified Electracraft right away and were able to find out what line it was and clean out al the epoxy. the remaining anchors in-between the RO equipment were set with out incident. 7 Daniel Ford No 60-PRODUCT WATER AREA>61-Product Water Area - Calcite Contactor We were installing pipe supports for the PVC pipes in this area today. 8 Daniel Ford No 20-HEADWORKS AREA We are working on the FRP cover at the safe box 9 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area and are sacking the exposed edge. 10 Daniel Ford No 30-TREATMENT AREA>31- Treatment Area - BNR Basins We pumped water out and fixed a leak in the slide gated in the north section of the BNR tank. the weak has been fixed and we refilled the tank. We are also welding the 8" and 6" SS air pipe to set tomorrow 11 Daniel Ford No 12-SITE OVERALL - YARD PIPING We finished working on the 3" WAS line near th dewatering. The Chemical duct bank near the Calcite contactors was finished The 14" PRN line was exposed (4 hours) We also exposed the 14" ROC line 12 Daniel Ford No 70-RESIDUALS AREA>73- Residuals Area - SAFE Filter System We installed about 20 feet of pipe at the safe filter.   MANPOWER LOG 33 Workers  |   272.0 Man Hours No.Contact/Company Workers # Hours Man Hours Location     1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:SUPERINTENDENT Troy Rosevear Created By:  Monica Weiss    2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:GENERAL FOREMAN Daniel Ford Created By:  Monica Weiss      FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:20 AM PST        No.Contact/Company Workers # Hours Man Hours Location     3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:CARPENTER FOREMAN Phil Lacey Created By:  Monica Weiss    4 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL     Notes:LABORER FOREMAN Ricardo Belmontez Created By:  Monica Weiss    5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL     Notes:JOURNEYMAN LABORERS Martin Castillo Angel Diaz Charlie Gonzalez Manny Hernandez Hector Sanchez Created By:  Monica Weiss    6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL     Notes:LABORER APPRENTICE Teddy Maldonado Johnathan Torres Created By:  Monica Weiss    7 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL     Notes:JOURNEYMAN CARPENTERS Orlando Cortez Rick Jenne Coy Bright Created By:  Monica Weiss    8 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL     Notes:CARPENTER APPRENTICE Pablo Campoverde Micah Pixley Created By:  Monica Weiss    9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:CEMENT MASON Daniel Sechslingloff Harry Vanderhoofven Created By:  Monica Weiss      FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:20 AM PST        No.Contact/Company Workers # Hours Man Hours Location     10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:Certified Welder Pipefitter Rick Dayton Created By:  Monica Weiss    11 J.R. Filanc Construction Company, Inc.2 8.0 16.0     Notes:APPRENTICE CEMENT MASON Adolfo Campoverde Created By:  Monica Weiss    12 J.R. Filanc Construction Company, Inc.1 8.0 8.0     Notes:OPERATOR APPRENTICE Joe (Trevor) Hernandez Created By:  Monica Weiss    13 ELECTRICRAFT, INC.8 8.0 64.0     Notes:Created By:  Rick Howland   14 Parada Painting Inc.2 9.0 18.0 95-OPERATIONS BUILDING     Notes:Touch up walls finish door frames Created By:  Monica Weiss       33  272.0    Manpower Log's Attachments:  13.  ELECTRICRAFT, INC.    11-8-2021 Daily Report.xls   14.  Parada Painting Inc.  2021.11.08 DFR.pdf   FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:20 AM PST          EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 United Rental 8.0 0.0 No   06:05AM  00-GENERAL  Notes:18000 pound mini excavator Created By: Daniel Ford   2 AHERN RENTAL 8.0 No   01:10PM  00-GENERAL  Notes:JCB Created By: Daniel Ford   3 United Rental 8.0 No   12:20PM  00-GENERAL  Notes:Scissor lift Created By: Daniel Ford   4 AHERN RENTAL 8.0 No   05:40AM    Notes:Scissor lift Created By: Daniel Ford   5 United Rental 8.0 No   03:05PM  00-GENERAL  Notes:24k generator Created By: Daniel Ford   6 United Rental 8.0 No   05:40AM    Notes:loader Created By: Daniel Ford   7 AHERN RENTAL 8.0 No   05:40AM    Notes:45' ariel lift Created By: Daniel Ford   8 United Rental 8.0 No   02:00PM  00-GENERAL  Notes:Telescoping Forklift Created By: Daniel Ford     DELIVERY LOG No.Time Delivery From Tracking Number Contents   1 11:55AM   PACIFIC COAST BOLT CORP 1091688 7 Boxes Bolts    Comments:Created By: Matt King 2 11:55AM   PACIFIC COAST BOLT CORP 1091700 Gaskets    Comments:Created By: Matt King   FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:20 AM PST        Delivery Log's Attachments: 1.  2021.11.08 Pac Coast Bolt 1091688.pdf 2.  2021.11.08 Pac Coast Bolt 1091700 30in gasket.pdf   WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 52°F 62°F 56°F 0.00 in.0.00 in.0.00 in.42%62%84%43°F 6.8 mph 11 mph 17 mph   DAILY SNAPSHOT 06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM Clear   52°F Clear   58°F Clear   60°F Partly Cloudy   60°F Partly Cloudy   56°F Cloudy   56°F   OBSERVED WEATHER CONDITIONS No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea     FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:20 AM PST          OBSERVED WEATHER CONDITIONS 1 06:35:00 AM No       By  Date  Copies To   FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:20 AM PST