Daily Log: Tuesday 11/9/2021
Daily Log Completed
The Daily Log was completed by Monica Weiss on Mon Dec 13, 2021 at 03:40pmPST.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Electra craft was running the main electricity all over the site
today.
We worked on cleaning up area 17 and organizing the yard.
We also stayed late and cleaned the street entrance from al
the traffic and mud leaving the job
RK&G removed their connex yesterday
we are sacking and packing all exposed concrete edges of the
concrete slabs
2 Daniel Ford No SAFETY We discussed crane safety and signals, muddy conditions,
slips, trips, and falls as well as proper lifting
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We worked on the 36 inch inch mixed liquor pipe on the east
side of the MBR cassette tank today.
4 Daniel Ford No 95-OPERATIONS
BUILDING
Pristine was on site to fix any cracks and damage to the
concrete floor. We modified and installed the TV mount
5 Daniel Ford No 96-MAINTENANCE
BUILDING
We cleaned this building.
Kenects still has a lot of tape residue on the floors that will
have to be det with before Pristine can do there work here.
6 Daniel Ford No 50-RO/UV BUILDING We worked on the the RO/UV anchors and started moving the
pipe supports into the building.
7 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We were installing pipe supports for the PVC pipes in this area
today.
8 Daniel Ford No 20-HEADWORKS AREA We are working on the FRP cover at the safe box
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:20 AM PST
NOTES LOG
No.Created By Issue?Location Comments
9 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area
and are sacking the exposed edge.
10 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We took measurements on the water level in the morning,
there are no visible leaks in either slide gate and the RAZ pipe.
equipment was moved to different locations in the tank and
we were able to continue installing the 6" and 8" air stainless
steel air line.
as well as continue with the FRP baffles.
11 Daniel Ford No 12-SITE OVERALL - YARD
PIPING The Chemical duct bank near the Calcite contactors was
finished and backfilled
MANPOWER LOG 30 Workers | 252.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Monica Weiss
2 J.R. Filanc Construction Company, Inc.1 10.0 10.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Monica Weiss
3 J.R. Filanc Construction Company, Inc.1 10.0 10.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Monica Weiss
4 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Monica Weiss
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:20 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Monica Weiss
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Monica Weiss
7 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Monica Weiss
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhoofven
Created By: Monica Weiss
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Monica Weiss
11 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Monica Weiss
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:20 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Monica Weiss
13 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
14 Parada Painting Inc.2 9.0 18.0 96-MAINTENANCE
BUILDING
Notes:Doors
Created By: Monica Weiss
30 252.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
11-9-2021 Daily Report.xls
14. Parada Painting Inc.
2021.11.09 DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:20 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:50AM Office Depot 676579 Paper
Comments:Created By: Matt King
2 12:35PM Capital Flow 12157 4" PVC Bird screen
Comments:Created By: Matt King
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:20 AM PST
1.
2021.11.09 Office Depot.pdf
2.
2021.11.09 Capflo MR118 Frogwall.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 61°F 57°F 0.15 in.0.15 in.0.15 in.65%89%98%54°F 5.3 mph 10 mph 16 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Rain
53°F
Rain
55°F
Rain
60°F
Cloudy
61°F
Partly Cloudy
59°F
Partly Cloudy
59°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No