HomeMy WebLinkAbout2021-11-12FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 11/12/2021
Daily Log Completed
The Daily Log was completed by Monica Weiss on Mon Dec 13, 2021 at 03:56pmPST.
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Electra craft was running the main electricity all over the site
today.
JD Dewer was on site to fix the diesel tank
We put the RO feed line under 50 lbs of pressure. It is holding
and Steve Mimaga has verified the test.
We drained a few feet of water, fixed the gate at the BNR tank,
and refilled the tank. It is holding and Steve Mimaga has
verified the test.
There was a third party surveyor on site verifying where the
easement is.
Floor connection was on site to take care of the punch list
items in the opps building as well as complete the instal in the
maintenance building.
We called off the rental wheelhouse forklift and jib this
morning
2 Daniel Ford No SAFETY We discussed crane safety and signals, muddy conditions,
slips, trips, and falls as well as proper lifting.
We also talked about not being lack about safety due to it
being friday we talked about keeping your head in the game
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We did layout and installed temp pipe supports and some
steel piping.
FBV Morro Bay Joint Venture Page 1 of 10 Printed on 1/24/2023 at 09:21 AM PST
NOTES LOG
No.Created By Issue?Location Comments
4 Daniel Ford No 95-OPERATIONS
BUILDING
We swept and cleaned all the floors.
In the areas of the TV mount where we made adjustments we
painted it and cleaned the entire mount.
Floor connection was on site to install the missing base and to
fix any problems in this building
5 Daniel Ford No 96-MAINTENANCE
BUILDING
Kenects is still installing bathroom fixtures in the unisex
bathroom.
Kenects still has a lot of tape residue on the floors that will
have to be delt with before Pristine can do there work here.
6 Daniel Ford No 50-RO/UV BUILDING We worked on the the RO/UV anchors and started moving the
pipe supports into the building.
7 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
no work in this area today
8 Daniel Ford No 20-HEADWORKS AREA no work in this area today
9 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area
and are sacking the exposed edge.
10 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We lowered the water in the north tank to fix the leaky gate.
The seal was adjusted, and we filled the tank back up. It
appears to be holding with no visible leaks. We filled the
evaporation pan and took a picture of the measurement and
sent it to Steve Mimaga.
We continued installing the 6" and 8" air stainless steel air line.
as well as continue with the FRP baffles.
11 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We put the 18" RO feed line under pressure. It is holding true
at 50 psi. We informed Steve Mimaga and sent him pictures of
the test.
MANPOWER LOG 12 Workers | 61.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.0 0.0 0.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 10 Printed on 1/24/2023 at 09:21 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.1 6.0 6.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.0 0.0 0.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.0 9.0 0.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 5.0 15.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Charlie Gonzalez
Manny Hernandez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 5.0 5.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 5.0 15.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 5.0 10.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 10 Printed on 1/24/2023 at 09:21 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.0 0.0 0.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhoofven
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 5.0 5.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 5.0 5.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.0 0.0 0.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
12 61.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 10 Printed on 1/24/2023 at 09:21 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:50PM AERZEN USA CORPORATION 009238 Expansion Joints for Blowers
Comments:Created By: Matt King
2 12:50PM Capital Flow 1815263 Bolts at A71 Safe
Comments:Created By: Matt King
3 12:50PM Capital Flow 1821099 BNG A30
Comments:Created By: Matt King
4 12:50PM Cougartron INC 802 Steel Welding
Comments:Created By: Matt King
5 12:50PM FERGUSON ENTERPRISES LLC 8064303 DMJ
Comments:Created By: Matt King
6 12:50PM FERGUSON ENTERPRISES LLC 9433143 Catch Basin A95 Coupling
Comments:Created By: Matt King
7 12:50PM FERGUSON ENTERPRISES LLC 9571798 Hydrants
Comments:Created By: Matt King
8 12:50PM FERGUSON ENTERPRISES LLC 9588489 PVC Glue
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 5 of 10 Printed on 1/24/2023 at 09:21 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
9 12:50PM FERGUSON ENTERPRISES LLC 9595000 Link Seal at SHT
Comments:Created By: Matt King
10 12:50PM Miner's Ace Hardware 722397 Primer for Monitor Stand
Comments:Created By: Matt King
11 12:50PM HD Supply White Cap 44910576 Wall column form
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.12 Aerzen Blower Parts Expansion Joints.pdf
2.
2021.11.12 Capflo MR71 at SAFE.pdf
FBV Morro Bay Joint Venture Page 6 of 10 Printed on 1/24/2023 at 09:21 AM PST
3.
2021.11.12 Capflo MR96 A30 ML BNG.pdf
4.
2021.11.12 Cougartron Noxpower Welding Cleaning Pickling.pdf
5.
2021.11.12 Ferguson 24in DMJ.pdf
FBV Morro Bay Joint Venture Page 7 of 10 Printed on 1/24/2023 at 09:21 AM PST
6.
2021.11.12 Ferguson 9433143 Catch bason Drain A95 PVC Coupling.pdf
7.
2021.11.12 Ferguson 9571798 MR116 Hydrants.pdf
8.
2021.11.12 Ferguson 9588489 Field PVC Glue.pdf
FBV Morro Bay Joint Venture Page 8 of 10 Printed on 1/24/2023 at 09:21 AM PST
9.
2021.11.12 Ferguson 9595000 Link Seals at SHT.pdf
10.
2021.11.12 Miners 722397 Primer for Monitor Stand.pdf
11.
2021.11.12 White cap 44910576 Column form Lithion Grease.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
62°F 83°F 69°F 0.00 in.0.00 in.0.00 in.34%49%62%50°F 6.5 mph 9 mph 15 mph
FBV Morro Bay Joint Venture Page 9 of 10 Printed on 1/24/2023 at 09:21 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
65°F
Clear
70°F
Clear
79°F
Clear
84°F
Clear
63°F
Clear
63°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 10 of 10 Printed on 1/24/2023 at 09:21 AM PST