Daily Log: Monday 11/15/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Electra craft was running the main electricity all over the site
today.
We passed the pressure test for the RO feed line.
Excavation for Electracraft at the MBR and for the light pole at
the dewatering
2 Daniel Ford No SAFETY We discussed crane safety and signals, muddy conditions,
slips, trips, and falls as well as proper lifting and working at
heights.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
Modify air piping at the cassette tank as well as installing
supports on the top of the wall.
4 Daniel Ford No 95-OPERATIONS
BUILDING
cleaning
5 Daniel Ford No 96-MAINTENANCE
BUILDING
We cleaned this building.
Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
6 Daniel Ford No 50-RO/UV BUILDING We installed all t shaped pipe supports in the north side of the
RO/UV building
7 Daniel Ford No 20-HEADWORKS AREA We are working on the WWS line at the fine screens for the
safe box.
8 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area
and are sacking the exposed edge.
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
The eastern gate is still leaking so we will have to drain it and
do the repair again
equipment was moved to different locations in the tank and
we were able to continue installing the 6" and 8" air stainless
steel air line.
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:22 AM PST
NOTES LOG
No.Created By Issue?Location Comments
as well as continue with the FRP baffles.
MANPOWER LOG 27 Workers | 222.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.0 9.0 0.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.0 10.0 0.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:22 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
13 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
27 222.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
11-15-2021 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:22 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:10PM Capital Flow 0018058 6in 90MR73
Comments:Created By: Matt King
2 01:10PM Capital Flow 1821099 Bolts
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:22 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 01:10PM Capital Flow 1815263 Bolts
Comments:Created By: Matt King
4 01:10PM Legrand 0002779370 Monitor Mount
Comments:Created By: Matt King
5 01:10PM FedEx 93442 Monitor Brackets
Comments:Created By: Matt King
6 01:10PM Ryan Herco Flow Solutions 9804716 PVC A50
Comments:Created By: Matt King
7 01:10PM Trojan Technologies UV
Comments:Created By: Matt King
8 01:10PM HD Supply White Cap 44821964 Safety
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.15 Capflo CBW 6in 90 MR73 .pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:22 AM PST
2.
2021.11.15 Capflo Hodell MR96.pdf
3.
2021.11.15 CAPFLO Mr71 BN Hodell.pdf
4.
2021.11.15 Legrand Ext Monitor Mount.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:22 AM PST
5.
2021.11.15 Monitor Brackets.pdf
6.
2021.11.15 Ryan Herco PVC RO-UV.pdf
7.
2021.11.15 Trojan UV 5 Pallets.pdf
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:22 AM PST
8.
2021.11.15 White Cap 44821964 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 68°F 58°F 0.00 in.0.00 in.0.00 in.45%70%96%47°F 2.5 mph 5 mph 8 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
56°F
Clear
62°F
Partly Cloudy
65°F
Partly Cloudy
56°F
Partly Cloudy
55°F
Partly Cloudy
53°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:35:00 AM No
By Date Copies To