HomeMy WebLinkAbout2021-11-16FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 11/16/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We dug for Electracraft at the MBR (ground wire and backfill),
maintenance (groundwire),and a hour at the chem duct bank
We also removed concrete from a ro line
We moved some equipmane with the crane today and
brought the crane to area 17 to do some scheduled
maintenance on it
2 Daniel Ford No SAFETY We discussed crane safety and signals, muddy conditions,
slips, trips, and falls as well as proper lifting and working at
heights.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are modifying and installing stainless steel air piping at the
cassette tank as well as installing supports on the top of the
wall.
4 Daniel Ford No 95-OPERATIONS
BUILDING
no work here today.
5 Daniel Ford No 96-MAINTENANCE
BUILDING Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
6 Daniel Ford No 50-RO/UV BUILDING We laid out and build up the northern equipment pad for the
ro feed line supports
7 Daniel Ford No 20-HEADWORKS AREA We are working on the WWS line at the fine screens for the
safe box. We did a little grout pad for the small odor control
pump (Recirc pump). We continued to set the 6" pipe at the
safe filter box.
8 Daniel Ford No 90-CHEMICAL FACILITY We laid out the finish grade on the edge of the slab and area
and are sacking the exposed edge.
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We are pumping the water out of the northern BNR tank so
we can install the remaining RAS pipe and plug and test the 12
inch WWS line.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:26 AM PST
NOTES LOG
No.Created By Issue?Location Comments
10 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
We are installing the FLG adapters
MANPOWER LOG 28 Workers | 231.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.0 10.0 0.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:26 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhooven
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
13 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:26 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
28 231.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
11-16-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:26 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:35PM Airgas 1105469783 Shade
Comments:Created By: Matt King
2 01:35PM Airgas 1105474157 Argon Compressed
Comments:Created By: Matt King
3 01:35PM Harrington Industrial Plastics
LLC
004L3402-1 Butterfly valves Odor control
Comments:Created By: Matt King
4 01:35PM HD Supply White Cap 44783790 Frogwall Lumber
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.16 Airgas 1105469783 Shade.pdf
2.
2021.11.16 Airgas Argon 1105474157.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:26 AM PST
3.
2021.11.16 Harrington Odor Control BFV A20.pdf
4.
2021.11.16 White Cap 44783790 Frogwall Lumber.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
51°F 66°F 55°F 0.00 in.0.00 in.0.00 in.51%89%97%52°F 3.6 mph 6 mph 11 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
51°F
Clear
58°F
Clear
58°F
Partly Cloudy
59°F
Partly Cloudy
56°F
Partly Cloudy
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:26 AM PST
By Date Copies To