Daily Log: Thursday 11/18/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We dug in the spare line for the PG&E line on Teresa st. Al lot
of rock had to be chipped out to accomplish this.
We installed all the straw waddles that arrived today.
2 Daniel Ford No SAFETY We discussed crane safety and signals, muddy conditions,
slips, trips, and falls as well as proper lifting and working at
heights.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are modifying and installing stainless steel air piping at the
cassette tank as well as installing supports on the top of the
wall.
4 Daniel Ford No 95-OPERATIONS
BUILDING
signs were installed in this building today.
5 Daniel Ford No 96-MAINTENANCE
BUILDING Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
Signs were being installed as well.
6 Daniel Ford No 50-RO/UV BUILDING We laid out and build up the northern equipment pad for the
ro feed line supports
7 Daniel Ford No 20-HEADWORKS AREA the 4" PRW line has been as built.
All missing pieces for the safe filter box lid were located and
the FRP beam that was mis cut has been reordered.
8 Daniel Ford No 90-CHEMICAL FACILITY
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
All water has been pumped out of the northern BNR basin,
and all lifts have been charged
10 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
We are installing the FLG adapters.
We dug the ditch for the electricians between the dewatering
and the SHT.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:27 AM PST
MANPOWER LOG 28 Workers | 231.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Electrician
Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Monica Weiss
3 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Monica Weiss
4 J.R. Filanc Construction Company, Inc.0 10.0 0.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Monica Weiss
5 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Monica Weiss
6 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Charlie Gonzalez
Manny Hernandez
Hector Sanchez
Created By: Monica Weiss
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:27 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.3 9.0 27.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Coy Bright
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Monica Weiss
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Harry Vanderhooven
Created By: Monica Weiss
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Monica Weiss
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Monica Weiss
13 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Monica Weiss
28 231.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
11-18-2021 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:27 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:45PM ASAP 507109 Drawings
Comments:Created By: Matt King
2 01:45PM Environmental Dynamics
International (EDI)
81835 Bubble Diffusers
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:27 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 01:45PM FERGUSON ENTERPRISES LLC 5x6 Sleeve
Comments:Created By: Matt King
4 01:45PM FERGUSON ENTERPRISES LLC SO0194043 Flanges SAFE
Comments:Created By: Matt King
5 01:45PM HD Supply White Cap 44783790 Wrong size chamfer
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.18 ASAP Repro .pdf
2.
2021.11.18 EDI Aeration Bubble Diffusers.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:27 AM PST
3.
2021.11.18 Ferguson 5in 6in Sleeve GLV.pdf
4.
2021.11.18 Ferguson US Pipe MR107 SAFE.pdf
5.
2021.11.18 White Cap 44783790 RETURN Wrong Size Chamfer .pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 56°F 52°F 0.00 in.0.00 in.0.00 in.87%92%97%50°F 1.7 mph 4 mph 4 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:27 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
47°F
Cloudy
51°F
Cloudy
55°F
Cloudy
56°F
Cloudy
55°F
Cloudy
54°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:55:00 AM No
By Date Copies To