Daily Log: Friday 11/19/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We were cleaning up all the dirt pile around the job and
working on sub grading for paving.
We also clearing material and all construction trash all over
the site.
We were doing survey for the curbs starting up near the
maintenance building.
underground pipe testing is ongoing.
Form work and material prep is ongoing for the frog wall.
2 Daniel Ford No SAFETY We discussed working around moving equipment and talked
about the benefits of good housekeeping practices.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are modifying and installing stainless steel air piping at the
cassette tank as well as installing supports on the top of the
wall.
We were also working the blowers and piping the air feed
pipes.
We also installed the 6" drain line valve.
4 Daniel Ford No 95-OPERATIONS
BUILDING
signs were installed in this building today.
Flooring connection was on site taking care of the rubber base
5 Daniel Ford No 96-MAINTENANCE
BUILDING Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
Flooring connection was in this building making sure all base
was installed
6 Daniel Ford No 50-RO/UV BUILDING We stripped forms for equipment pads and pipe supports pad.
We also backfilled all holes in this area.
7 Daniel Ford No 20-HEADWORKS AREA No work in this area today.
8 Daniel Ford No 90-CHEMICAL FACILITY We cleaned up the area outside the building and were
working on the grades
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:27 AM PST
NOTES LOG
No.Created By Issue?Location Comments
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
All water has been pumped out of the northern BNR basin,
and all lifts have been charged
10 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
We are installing the FLG adapters.
11 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
We did some rework for the mode Air and fabricated supports
for the SHT.
MANPOWER LOG 28 Workers | 232.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 10.0 10.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:27 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Manny Hernandez
Hector Sanchez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Coy Bright
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 11.0 11.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:27 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
13 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
28 232.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
11-19-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:27 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 02:05PM FERGUSON ENTERPRISES LLC 9600407 Chem A90 Plumbing
Comments:Created By: Matt King
2 02:05PM Grainger 6530371011 Sewage pump
Comments:Created By: Matt King
3 02:05PM Pacific Coast Bolt Corporation 1092141 Bolts
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.19 Ferguson Chem Area Plumbing MR120.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:27 AM PST
2.
2021.11.19 Grainger Sewage Pump.pdf
3.
2021.11.19 Pac Coast Bolt 1092141 MR127 ASBLT.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 59°F 55°F 0.00 in.0.00 in.0.00 in.77%87%96%51°F 5.2 mph 8 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
51°F
Partly Cloudy
54°F
Partly Cloudy
58°F
Partly Cloudy
59°F
Partly Cloudy
55°F
Partly Cloudy
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:27 AM PST
By Date Copies To