HomeMy WebLinkAbout2021-11-23FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 11/23/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We were cleaning up all the dirt pile around the job and
working on sub grading for paving.
We were doing survey for the curbs
Form work and material prep is ongoing for the frog wall.
2 Daniel Ford No SAFETY We had a all hands meeting today and the main topic was our
lock out tag out procedure.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are modifying and installing stainless steel air piping at the
cassette tank as well as installing supports on the top of the
wall.
We were also working the blowers and piping the air feed
pipes (modifying the 8" S.S. pipe for the air blowers.
We also installed the 6" and 8" drain line valve.
4 Daniel Ford No 95-OPERATIONS
BUILDING
No work in this area today
5 Daniel Ford No 96-MAINTENANCE
BUILDING
Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
Flooring connection was in this building making sure all base
was installed
6 Daniel Ford No 50-RO/UV BUILDING We stripped forms for equipment pads and pipe supports pad.
We also backfilled all holes in this area.
All piping and pipe supports have been moved beyond the
boundaries of the asphalt
7 Daniel Ford No 20-HEADWORKS AREA No work in this area today.-
8 Daniel Ford No 90-CHEMICAL FACILITY We cleaned up the area outside the building and were
working on the grades
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
All water has been pumped out of the northern BNR basin,
and all lifts have been charged
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:28 AM PST
NOTES LOG
No.Created By Issue?Location Comments
10 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
We are installing the FLG adapters.
11 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
We did some rework for the mode Air and fabricated supports
for the SHT.
MANPOWER LOG 31 Workers | 276.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 11.0 11.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 12.0 12.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 11.0 11.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 10.0 50.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Hector Sanchez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:28 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Coy Bright
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Raul Velasquez
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 11.0 11.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 11.0 11.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:28 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
13 ELECTRICRAFT, INC.9 8.0 72.0
Notes:Created By: Rick Howland
14 Parada Painting Inc.2 8.0 16.0 95-OPERATIONS
BUILDING
Notes:Containment Areas
Created By: Monica Weiss
31 276.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
11-23-2021 Daily Report.xls
14. Parada Painting Inc.
2021.11.23 DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:28 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:55AM Ferguson Enterprises, LLC 9549188-2 4in Spools MR111
Comments:Created By: Matt King
2 07:55AM Ferguson Enterprises, LLC 852322 Tyler U 6in 90
Comments:Created By: Matt King
3 07:55AM Ferguson Enterprises, LLC SO0194043 8x3.5 Filler Flange
Comments:Created By: Matt King
4 07:55AM Ferguson Enterprises, LLC SO0197496 12inx24in Spool A20
Comments:Created By: Matt King
5 07:55AM NEGRANTI & SONS 32695 Rip Rap
Comments:Created By: Matt King
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:28 AM PST
1.
2021.11.23 Ferguson 9549188-2 4in spools MR111 Dewater.pdf
2.
2021.11.23 Ferguson Tyler U 6in 90.pdf
3.
2021.11.23 Ferguson US Pipe 8x3.5 Filler Flg.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:28 AM PST
4.
2021.11.23 Ferguson US Pipe 12in x 24in Spool A20 MR 122.pdf
5.
2021.11.23 Negranti 32695 Rip Rap.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 66°F 60°F 0.00 in.0.00 in.0.00 in.30%54%83%42°F 4.8 mph 6 mph 11 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
60°F
Clear
63°F
Clear
61°F
Partly Cloudy
61°F
Partly Cloudy
56°F
Partly Cloudy
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:35:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:28 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 8 of 8 Printed on 1/24/2023 at 09:28 AM PST