Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 11/29/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We are working on the Bollards for PG&E and finishing the
grade the PG&E box off Teresa St.
The 24" pipe at the declore area is being bolted up.
4" clamps are being installed at the lift station.
Backfill around the pump station was happening today.
We also continued work on the level spreaders (installing
rocks)
We had one laborer cleaning out the"footing" for the frog wall.
2 Daniel Ford No SAFETY We had a all hands meeting today and the main topic was our
lock out tag out procedure.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We are bolting up the 6" SS ines at the cassette tank
We were also working the blowers and piping the air feed
pipes (modifying the 8" S.S. pipe for the air blowers.
We also installed the 6" and 8" drain line valve.
4 Daniel Ford No 95-OPERATIONS
BUILDING
No work in this area today
5 Daniel Ford No 96-MAINTENANCE
BUILDING
Kenects still has a lot of tape residue on the floors that will
have to be dealt with before Pristine can do there work here.
Flooring connection was in this building making sure all base
was installed
6 Daniel Ford No 50-RO/UV BUILDING We stripped forms for equipment pads and pipe supports pad.
We also backfilled all holes in this area.
All piping and pipe supports have been moved beyond the
boundaries of the asphalt
7 Daniel Ford No 20-HEADWORKS AREA No work in this area today.-
8 Daniel Ford No 90-CHEMICAL FACILITY We cleaned up the area outside the building and were
working on the grades
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:29 AM PST
NOTES LOG
No.Created By Issue?Location Comments
9 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We are bolting up the FBR- air manifold piping (ss)
10 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
We are installing the FLG adapters.
11 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
We did some rework for the mode Air and fabricated supports
for the SHT.
MANPOWER LOG 30 Workers | 241.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.9 8.0 72.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Monica Weiss
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Monica Weiss
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Monica Weiss
5 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:29 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Hector Sanchez
Created By: Monica Weiss
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Benjamin Marquez III
Created By: Monica Weiss
8 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Coy Bright
Created By: Monica Weiss
9 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Raul Velasquez
Created By: Monica Weiss
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CEMENT MASON
Daniel Sechslingloff
Created By: Monica Weiss
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:29 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Monica Weiss
13 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Monica Weiss
30 241.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
11-29-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:29 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:05AM CalPortland 1708882 Pipe Encasement
Comments:Created By: Matt King
2 08:05AM Ferguson Enterprises, LLC 9615138 Sanitary Sewer Box
Comments:Created By: Matt King
3 08:05AM Ferguson Enterprises, LLC 9623927 Frogwall
Comments:Created By: Matt King
4 08:05AM HD Supply White Cap 45030677 Carpenter Material
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.11.29 Calportland pipe enc 1708882.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:29 AM PST
2.
2021.11.29 Ferguson 9615138 San Swr Box.pdf
3.
2021.11.29 Ferguson 9623927 Frogwall PRW.pdf
4.
2021.11.29 White Cap Carpenter 45030677.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 62°F 57°F 0.00 in.0.00 in.0.00 in.37%61%85%45°F 4.2 mph 9 mph 10 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:29 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
57°F
Clear
59°F
Clear
63°F
Clear
61°F
Clear
58°F
Clear
61°F
OBSERVED WEATHER CONDITIONS