HomeMy WebLinkAbout2021-12-07FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 12/7/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We were cutting grade for Granite. We also were moving
material all over the job to make way for Granite, and we
continued with the wattles being installed.
We are potholing to find leaks in some underground pipes we
are testing.
2 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
The 4" spools were being installed today. We are working and
installing the expansion at the water tank 10" drilling out the
holes
3 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
The masons continue sacking, patching, and bushinging the
top of the SHT walls.
We are continuing with the supports for the 2" PVC lines.
4 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We exposed the leaking 4" PRW pipe for repair near the lower
head works area.
5 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We are working on the pvc pipe supports.
Two 8"x 2" saddles at the Calcite contactors
We are bolting up the 20" DMJ at balance tank.
We reworked the 6" spool for the flow meter at the IPR.
MANPOWER LOG 36 Workers | 290.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.5 8.0 40.0
Notes:Created By: Brody Gill
2 RARIG CONSTRUCTION, INC.3 8.0 24.0
Notes:Roof prep
Created By: Michael Rarig
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:33 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
3 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Charlie Gonzales
Estevan, Zamudio
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Teddy Maldonado
Benjamin Marquez III
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Coy Bright
Donn Bunte
Orlando Cortez
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:33 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micah Pixley
Pablo Campoverde
Raul Velasquez
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
13 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
36 290.0
Manpower Log's Attachments:
1. Granite Construction Inc.
GCC Daily Report 12.6.21.pdf
3. ELECTRICRAFT, INC.
12-7-2021 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:33 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:25AM DEZURIK INC 624858 6" BFV & 12" BFV
Comments:Created By: Matt King
2 09:25AM Ferguson Enterprises, LLC 9600407-3 Chem Plumbing
Comments:Created By: Matt King
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:33 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
3 09:25AM Ferguson Enterprises, LLC 862217 SWR Relief Valve
Comments:Created By: Matt King
4 09:25AM Ferguson Enterprises, LLC 962217 6in PVC Fittings
Comments:Created By: Matt King
5 09:25AM Ferguson Enterprises, LLC Handwheel - No packing slip
Comments:Created By: Matt King
6 09:25AM Miner's Ace Hardware 724539 Area 30 Piping
Comments:Created By: Matt King
7 09:25AM Miner's Ace Hardware 724538 Safety lunch gifts
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.12.07 Dezurik CSAMSCO BFV MR79_A63.pdf
2.
2021.12.07 Ferguson 9600407-3 Chem Plumbine.pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:33 AM PST
3.
2021.12.07 Ferguson 9615138-2 SWR Relief Valve.pdf
4.
2021.12.07 Ferguson FREQ 6in PVC Fittings 9637409.pdf
5.
2021.12.07 Ferguson Handwheel.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:33 AM PST
6.
2021.12.07 Miners 724539 A30 Piping.pdf
7.
2021.12.07 Miners Safety Lunch 724538.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 59°F 55°F 0.02 in.0.02 in.0.02 in.70%84%93%51°F 4.2 mph 5 mph 8 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
54°F
Partly Cloudy
55°F
Partly Cloudy
59°F
Partly Cloudy
59°F
Partly Cloudy
56°F
Partly Cloudy
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:00:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:33 AM PST