Daily Log: Wednesday 12/8/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL The grade ate the entrance and at the electrical was being
worked on today.We also did some work on the electrica line
in that same area.
Pressure testing continues throughout the site.
2 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
The 4" spools were being installed today. We are working and
installing the expansion at the water tank 10" drilling out the
holes
3 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
The masons continue sacking, patching, and bushinging the
top of the SHT walls.
We are continuing with the supports for the 2" PVC lines.
4 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We exposed the leaking 4" PRW pipe for repair near the lower
head works area.
5 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
We are working on the pvc pipe supports.
Two 8"x 2" saddles at the Calcite contactors
We are bolting up the 20" DMJ at balance tank.
We reworked the 6" spool for the flow meter at the IPR.
6 Daniel Ford No 50-RO/UV BUILDING Pipe supports are being fabricated and we are welding the
base plates
7 Daniel Ford No 60-PRODUCT WATER
AREA>63-Product Water -
IPR Product Water Pump
Station
The 12" and 6" auto BV at the IPR are being installed
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 09:34 AM PST
MANPOWER LOG 37 Workers | 289.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.5 8.0 40.0
Notes:Created By: Brody Gill
2 RARIG CONSTRUCTION, INC.3 5.0 15.0
Notes:Roof prep
Created By: Michael Rarig
3 ELECTRICRAFT, INC.7 8.0 56.0
Notes:Created By: Rick Howland
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:LABORER FOREMAN
Ricardo Belmontez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Charlie Gonzales
Estevan, Zamudio
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 09:34 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Teddy Maldonado
Benjamin Marquez III
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Coy Bright
Donn Bunte
Orlando Cortez
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micah Pixley
Pablo Campoverde
Raul Velasquez
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.2 8.0 16.0
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
13 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
37 289.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 09:34 AM PST
1. Granite Construction Inc.
GCC Daily Report 12.7.21.pdf
3. ELECTRICRAFT, INC.
12-8-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 United Rental 8.0 No 05:40AM
Notes:loader
Created By: Daniel Ford
7 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 09:34 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
8 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 09:35AM CalPortland 1712673 Frogwall
Comments:Created By: Matt King
Delivery Log's Attachments:
1.
2021.12.08 Calportland Frogwall 1712673.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 58°F 54°F 0.00 in.0.03 in.0.03 in.72%83%93%49°F 4.2 mph 6 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
51°F
Clear
53°F
Partly Cloudy
58°F
Partly Cloudy
57°F
Partly Cloudy
55°F
Partly Cloudy
58°F
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 09:34 AM PST
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 12:55:00 PM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 09:34 AM PST