No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We re worked the entire front entrance of the job site, as well
as continued with the BMP 's and cleaning up the entire site
after the rain event over the last 2 days.
We also continued with straw waddles in the ravine and along
the eastern edge of th swale for the ravine.
2 Daniel Ford No 20-HEADWORKS AREA We were installing the FRP cover for the safe filter box
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We pumped out the water from all the bnr tanks today.
routing it down the swales to pond 1. we laid out the aeration
anchors and brackets in the west basin Allied Steel aso
expended the platform and is working on the hand rail on the
southern edge of the catwalk platform.
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
Allied steel is working on all platforms, stairs, and handrail for
the MBR cassette tank.
5 Daniel Ford No 50-RO/UV BUILDING We are working on pipe supports, anchors, and installation,
and putting together all PVC in this building
6 Daniel Ford No 17-OUTDOOR STORAGE
AREA
We got the total station on site today and laid out the finish
grade in building 14,15,and 17
7 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
MANPOWER LOG 26 Workers | 208.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 09:36 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Hector Sanchez
Estevan Zamudio
Charlie Gonzales
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Benjamin Marquez III
Jonathan Pratt
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenne
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micah Pixley
Raul Velasquez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 09:36 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:APPRENTICE CEMENT MASON
Samuel Rannals
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:OPERATOR APPRENTICE
Joe (Trevor) Hernandez
Created By: Daniel Ford
11 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
26 208.0
Manpower Log's Attachments:
11. ELECTRICRAFT, INC.
12-15-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 09:36 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
41°F 56°F 47°F 0.00 in.0.90 in.2.36 in.57%71%80%38°F 4.0 mph 6 mph 8 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
41°F
Partly Cloudy
45°F
Clear
53°F
Clear
57°F
Clear
50°F
Partly Cloudy
47°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
By Date Copies To