1 Daniel Ford No 00-GENERAL We did some work on the entrance in the front. We also
worked on a bunch of clean up and organizing all over the
site.
We started taking out all the mud out of the areas near the RO
building and the Chemical building
2 Daniel Ford No 20-HEADWORKS AREA We were installing the FRP cover for the safe filter box
3 Daniel Ford No 50-RO/UV BUILDING We are working on pipe supports, anchors, and installation,
and putting together all PVC in this building.
The 2" flanges outside of the building (for the chemical
containment piping) are being installed.
4 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
MANPOWER LOG 26 Workers | 197.5 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 RARIG CONSTRUCTION, INC.3 6.5 19.5
Notes:Unload and leak repair
Created By: Michael Rarig
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:37 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.1 7.0 7.0 00-GENERAL
Notes:CARPENTER FOREMAN
Phil Lacey
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Estevan Zamudio
Charlie Gonzales
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Benjamin Marquez III
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Brian Egin
Rick Jenn
Orlando Cortez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Raul Velasquez
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 3.0 3.0
Notes:APPRENTICE CEMENT MASON
Samuel Rannals
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:37 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
11 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
26 197.5
Manpower Log's Attachments:
11. ELECTRICRAFT, INC.
12-17-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:37 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:20AM AIRGAS 3182
Comments:Created By: Monica Weiss
2 07:20AM Ferguson Enterprises, LLC 656696-1 PVC
Comments:Created By: Monica Weiss
3 07:20AM Ferguson Enterprises, LLC 0662974 SCH80 4*2*2 Tee
Comments:Created By: Monica Weiss
4 07:20AM Ferguson Enterprises, LLC 9665627 3" sch 80 90 ell
Comments:Created By: Monica Weiss
5 07:20AM Ferguson Enterprises, LLC 9665657 4X2 Flush Bushing (Returned)
Comments:Created By: Monica Weiss
6 07:20AM Ferguson Enterprises, LLC CM036505
Comments:Created By: Monica Weiss
7 07:20AM Perry's Automotive Truck repair failed smog
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2021.12.17 Airgas 3182.pdf
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:37 AM PST
2.
2021.12.17 Ferguson 656696-1 PVC.pdf
3.
2021.12.17 Ferguson 0662974.pdf
4.
2021.12.17 Ferguson 9665627.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:37 AM PST
5.
2021.12.17 Ferguson 9665657.pdf
6.
2021.12.17 Ferguson CM036505.pdf
7.
2021.12.17 Perrys Auto.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 54°F 49°F 0.00 in.0.32 in.0.32 in.64%72%80%40°F 6.6 mph 12 mph 20 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:37 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
46°F
Clear
49°F
Clear
52°F
Clear
54°F
Clear
50°F
Clear
49°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:30:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:37 AM PST