HomeMy WebLinkAbout2021-12-21FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 12/21/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL We did some work on the entrance in the front. We also
worked on a bunch of clean up and organizing all over the
site.
We started taking out all the mud out of the areas near the RO
building and the Chemical building.
Pipe testing continues.
2 Daniel Ford No 20-HEADWORKS AREA We were installing the FRP cover for the safe filter box
3 Daniel Ford No 50-RO/UV BUILDING We are working on pipe supports, anchors, and installation,
and putting together all PVC in this building.
The 2" flanges outside of the building (for the chemical
containment piping) are being installed.
4 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
5 Daniel Ford No 20-HEADWORKS AREA We were drilling and anchoring and grouting the supports at
the head works.
Work on the safe filter box cover continues.
We are workin g on the yard piping in both the upper and
lower head works. We also flipped the the 12" auto valve for
the fine screens.
6 Daniel Ford No 60-PRODUCT WATER
AREA>64-Product Water -
Outfall Pump Station
Bolts were being installed in this area
7 Daniel Ford No 95-OPERATIONS
BUILDING
The TVs are all mounted in this building
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:39 AM PST
MANPOWER LOG 35 Workers | 275.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.4 8.0 32.0
Notes:Created By: Brody Gill
2 RARIG CONSTRUCTION, INC.6 8.0 48.0
Notes:Roofing
Created By: Michael Rarig
3 RARIG CONSTRUCTION, INC.4 8.0 32.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Roof prep
Created By: Michael Rarig
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Estevan Zamudio
Charlie Gonzales
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Benjamin Marquez III
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:39 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Raul Velasquez
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 3.0 3.0
Notes:APPRENTICE CEMENT MASON
Samuel Rannals
Created By: Daniel Ford
11 ELECTRICRAFT, INC.7 8.0 56.0
Notes:Created By: Rick Howland
35 275.0
Manpower Log's Attachments:
1. Granite Construction Inc.
GCC Daily Report 12.20.21.pdf
11. ELECTRICRAFT, INC.
12-21-2021 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:39 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:00AM Capital Flow 12464 IPR Tank Connection
Comments:Created By: Monica Weiss
2 08:00AM Environmental Dynamics
International (EDI)
Area 70 SS Drop Legs
Comments:Created By: Monica Weiss
3 08:00AM Ferguson Enterprises, LLC 9666043 3in sch 80 90ell / 4*2 bushings
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:39 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
4 08:00AM Miner's Ace Hardware 725768 SILT FENCING
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2021.12.21 CapFlo 12464 IPR Tank Connection.pdf
2.
2021.12.21 EDI SS Drop Legs A70 .pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:39 AM PST
3.
2021.12.21 Ferguson 9666043 .pdf
4.
2021.12.21 Miners Silt Fence 725768.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
43°F 57°F 50°F 0.00 in.0.00 in.0.00 in.56%69%77%40°F 3.6 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
45°F
Partly Cloudy
49°F
Partly Cloudy
57°F
Partly Cloudy
57°F
Partly Cloudy
52°F
Partly Cloudy
48°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 09:00:00 AM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:39 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:39 AM PST