HomeMy WebLinkAbout2021-12-29FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 12/29/2021
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL The front entrance was all cleaned up and reworked today.
Water samples were taken in all 5 discharge locations and
pictures were uploaded to procore morning and noon
Pipe testing continues.
We are fabricating the 2" galvanized pipes for the hose bibs
We fixed the fence the fences around the job
As well as cleaning out the level spreaders.
We took care of cord repair and misc safety items
we were working on shelf and conex organization.
2 Daniel Ford No 50-RO/UV BUILDING We are fabricating the 8" pvc pipes and we tested haf of the 2"
chemical lines outside of the containment pipe.
We were also working on the the heater install and the mixer
for the neutralizer tank.
We were also working on anchoring down tanks
3 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
MANPOWER LOG 22 Workers | 168.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 09:43 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Charlie Gonzales
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Ben Marquez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don butte
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 0.0 0.0
Notes:APPRENTICE CEMENT MASON
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
9 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 09:43 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
22 168.0
Manpower Log's Attachments:
9. ELECTRICRAFT, INC.
12-29-2021 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 09:43 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
47°F 54°F 50°F 0.59 in.0.63 in.1.00 in.83%86%92%46°F 8.4 mph 14 mph 22 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Rain
48°F
Rain
49°F
Rain
51°F
Rain
54°F
Rain
52°F
Rain
52°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 08:15:00 AM No
By Date Copies To