HomeMy WebLinkAbout2022-01-03FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 1/3/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Job site clean up
We were pumping water out of the cassette tanks, the BNR
and the chemical building today.
We were working on the shelfs in the PVC container
pipe supports and misc equipment were being grouted today
Survey continues around the site
2 Daniel Ford No 50-RO/UV BUILDING We are fabricating the 8" pvc pipes and we tested haf of the 2"
chemical lines outside of the containment pipe.
3 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We were installing bolts in the MBR area.
We monuted the compressor valve train as well as the strut
supports.
We were drilling and installing the anchor supports in this
area.
We also were working on the compressor canopy
5 Daniel Ford No 20-HEADWORKS AREA Removed broken threads for the headworks valve (back
charge to Kusters)
The 1 inch pvc for the PRW line was being installed
6 Sean Ferguson No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Received materials and boom lift started vents.
MANPOWER LOG 37 Workers | 296.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.7 8.0 56.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Angel Diaz
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Benjamin Marquez
Hector Schanez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Ben Marquez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don butte
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Mikah Pixley
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Journey Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
11 5 8.0 40.0
Notes:Roofing and wall sheeting
Created By: Michael Rarig
12 ELECTRICRAFT, INC.7 8.0 56.0
Notes:Created By: Rick Howland
13 Knecht's Plumbing & Heating, Inc.1 8.0 8.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Sean Ferguson
37 296.0
Manpower Log's Attachments:
12. ELECTRICRAFT, INC.
1-3-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:44 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:40AM Miner's Ace Hardware RO/UV Parts and Fittings
Comments:Created By: Monica Weiss
2 11:40AM Ferguson Enterprises, LLC U-Bolts A60
Comments:Created By: Monica Weiss
3 11:40AM Harrington Industrial Plastics
LLC
004L4223-3 & 2
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:44 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
4 11:40AM Miner's Ace Hardware 726584 RO RO Fittings
Comments:A60
Created By: Monica Weiss
5 11:40AM PACIFIC COAST BOLT CORP 1093109 Misc Bolts for completing areas
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.02 Miners RO.pdf
2.
2022.01.03 Ferguson U-Bolts A60.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:44 AM PST
3.
2022.01.03 Harrington 004L4223-3 & 2.pdf
4.
2022.01.03 Miners 726584 RO .pdf
5.
2022.01.03 Pac Coast Bolt 1093109.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
43°F 54°F 48°F 0.00 in.0.00 in.0.00 in.72%83%91%43°F 4.5 mph 7 mph 12 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:44 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
44°F
Partly Cloudy
46°F
Partly Cloudy
53°F
Partly Cloudy
55°F
Partly Cloudy
51°F
Partly Cloudy
47°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 09:10:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:44 AM PST