Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 1/4/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Exposing and repairing ground wire at various locations
around the job.
Watering the hydro seed site wide.Some backfiling happened
at pond 1.
Back filling and grading was happening at near the outfall
area.
Bolts for the declor T section.
We are working on shelves and organizing the connexes.
2 Daniel Ford No 50-RO/UV BUILDING We are fabricating the 8" pvc pipes and we tested haf of the 2"
chemical lines outside of the containment pipe.
3 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
We were installing bolts in the MBR area.
We monuted the compressor valve train as well as the strut
supports.
We were drilling and installing the anchor supports in this
area.
We also were working on the compressor canopy
5 Daniel Ford No 20-HEADWORKS AREA We fabricated and were installing the the PRW line for the
section of piping we worked on the 3" to 1" to 1/2 piping.
Supports for the PRW linje are being installed.
Anchoring continues for the foul air system
Anchors are being set for the fine screens.
6 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We exposed detected and repaired a leak in the FBN system
just east of the SHT.
7 Daniel Ford No 60-PRODUCT WATER AREA Bolts and the 20" spacer are being installed.
We set up forms and grouted under the 3 IPR pumps and 2 of
the outfall pumps.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:44 AM PST
NOTES LOG
No.Created By Issue?Location Comments
8 Sean Ferguson No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Started running vents and laying out water.
MANPOWER LOG 38 Workers | 304.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.4 8.0 32.0
Notes:Created By: Brody Gill
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Martin Castillo
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Hector Schantz
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Ben Marquez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don butte
Rick Jenne
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Mikah Pixley
Raul velasquez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Journey Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
12 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
13 Knecht's Plumbing & Heating, Inc.2 8.0 16.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Sean Ferguson
38 304.0
Manpower Log's Attachments:
1. Granite Construction Inc.
GCC Daily Report 1.3.22.pdf
12. ELECTRICRAFT, INC.
1-4-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:44 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:55AM Harrington Industrial Plastics
LLC
8030224 A50 & A90 PVC CPVC
Comments:Created By: Monica Weiss
2 11:55AM Harrington Industrial Plastics
LLC
004L4223-1 A50 & A90 PVC CPVC
Comments:Created By: Monica Weiss
3 11:55AM Miner's Ace Hardware 726679 HDW & PRW
Comments:A20
Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:44 AM PST
1.
2022.01.04 Harrington A50_A90.pdf
2.
2022.01.04 Harrington.pdf
3.
2022.01.04 Miners 726679 HDW PRW.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 58°F 51°F 0.00 in.0.00 in.0.00 in.68%85%93%47°F 4.6 mph 9 mph 15 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:44 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
45°F
Partly Cloudy
50°F
Clear
56°F
Clear
57°F
Partly Cloudy
54°F
Clear
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:55:00 AM No