HomeMy WebLinkAbout2022-01-05FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 1/5/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL Rock and wattles were being installed and we are dealing with
improvements to our Swppp program.
The watering of the hydroseeding is ongoing.
We have re worked the front entrance this morning.
We are working on shelves and organizing the connexes.
Bolts were being installed at the declor piping.
2 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
We are doing pressure testing on the WWS, PRW, and the pw
lines
3 Daniel Ford No 20-HEADWORKS AREA We were fabricating and installing supports at the headworks
as well as the PRW
4 Daniel Ford No 12-SITE OVERALL - YARD
PIPING
pipe testing continues.
5 Daniel Ford No 60-PRODUCT WATER AREA We were grouting pumps, and drilling and epoxing in the
outfall pumps.
6 Daniel Ford No 95-OPERATIONS
BUILDING
We were moving excess dirt and spoils aso working on the sub
grade from this area so granite could continue their work.
7 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We were installing the blower lines and the defussersers
8 Sean Ferguson No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Continue vents and water.
MANPOWER LOG 43 Workers | 329.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 RARIG CONSTRUCTION, INC.5 5.0 25.0
Notes:Wall sheeting and trim
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Michael Rarig
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:GENERAL FOREMAN
Daniel Ford
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Hector Schantz
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Ben Marquez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don Butte
Rick Jenne
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Raul Vasquez
Mikah Pixley
Raul velasquez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 09:44 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Journey Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
12 Granite Construction Inc.4 8.0 32.0
Notes:Created By: Brody Gill
13 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
14 Knecht's Plumbing & Heating, Inc.2 8.0 16.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Sean Ferguson
43 329.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 09:44 AM PST
12. Granite Construction Inc.
GCC Daily Report 1.4.22.pdf
13. ELECTRICRAFT, INC.
1-5-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 AHERN RENTAL 8.0 No 01:10PM 00-GENERAL
Notes:JCB
Created By: Daniel Ford
3 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
4 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
5 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
7 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 09:44 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:05PM Ferguson Enterprises, LLC MR133 Expansion Joints
Comments:Created By: Monica Weiss
2 12:05PM NEGRANTI & SONS 33285 1.5 Rock
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.05 Ferguson MR133 Exp Joints.pdf
2.
2022.01.05 Negranti 33285 1.5 Rock .pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 09:44 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 62°F 55°F 0.00 in.0.00 in.0.00 in.57%71%82%46°F 8.6 mph 12 mph 20 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
51°F
Partly Cloudy
53°F
Clear
59°F
Clear
63°F
Clear
58°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:40:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 09:44 AM PST