Daily Log: Thursday 1/6/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Troy Rosevear No 00-GENERAL - The watering of the hydro seeding is ongoing.Continued
Watering the Hydro Seed.
- Continued cleaning and repairing BMP's throughout the Site.
- Laid down hay on the rock surface that we can install straw
waddles on, on the west side of the Operations on the cut
slope.
- Repair ruts and gullies around the sites hillsides from the last
rain event.
- Surveyed roadways and curbs for Granite.
2 Troy Rosevear No 20-HEADWORKS AREA - Fabricated and installed supports and pie at the headwords
for Odor control and PRW.
3 Troy Rosevear No 60-PRODUCT WATER AREA We are still grouting pumps, drilling and installing anchors at
the outfall and IPR pump station.
4 Troy Rosevear No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
We were installing the blower lines, defuser piping and
anchors at the BNR Tank. Missing some items from the
vendor.
5 Sean Ferguson No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Continue vents and water.
6 Troy Rosevear No 30-TREATMENT AREA Installed PRW supports at the MBR tank.
MANPOWER LOG 39 Workers | 312.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.4 8.0 32.0
Notes:Created By: Brody Gill
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 RARIG CONSTRUCTION, INC.2 8.0 16.0 90-CHEMICAL
FACILITY
Notes:Roof prep
Created By: Michael Rarig
3 RARIG CONSTRUCTION, INC.2 8.0 16.0
Notes:Trim
Created By: Michael Rarig
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Hector Schantz
Created By: Troy Rosevear
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Troy Rosevear
6 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don Butte
Rick Jenne
Created By: Troy Rosevear
7 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Mikah Pixley
Created By: Troy Rosevear
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Troy Rosevear
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Troy Rosevear
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Troy Rosevear
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Troy Rosevear
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Journey Cement Mason
Daniel Sheslingoff
Created By: Troy Rosevear
13 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
14 Knecht's Plumbing & Heating, Inc.3 8.0 24.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Sean Ferguson
15 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:General Foreman
Daniel Ford
Created By: Troy Rosevear
39 312.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:45 AM PST
1. Granite Construction Inc.
GCC Daily Report 1.5.22.pdf
13. ELECTRICRAFT, INC.
1-6-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Troy Rosevear
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Troy Rosevear
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Troy Rosevear
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Troy Rosevear
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Troy Rosevear
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Troy Rosevear
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:45 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:05PM AHERN RENTALS - SANTA
MARIA
TRUCK RENTAL for Delivery
Comments:Rented truck to pick up Catch Basin at Midstate
Created By: Monica Weiss
2 12:05PM Capital Flow Spools US Pipe for IPR Tank
Comments:Created By: Monica Weiss
3 12:05PM Harrington Industrial Plastics
LLC
004L4223-5 chem PVC CPVC
Comments:Created By: Monica Weiss
4 12:05PM Harrington Industrial Plastics
LLC
Chem PVC CPVC RO
Comments:Created By: Monica Weiss
5 12:05PM MID-STATE CONCRETE
PRODUCTS, LLC
Catch Basin
Comments:Created By: Monica Weiss
6 12:05PM Miner's Ace Hardware 726907 Fine Screens PRW A20
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.06 Ahern Truck for Catch Basin.pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:45 AM PST
2.
2022.01.06 Capflo Spools US Pipe IPR Tank.pdf
3.
2022.01.06 Harrington 004l4223-5 Chem PVC.pdf
4.
2022.01.06 Harrington Chem PVC A50.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:45 AM PST
5.
2022.01.06 Mid-State Catch Basin.pdf
6.
2022.01.06 Miners 126907 Fine Screens PRW A20.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 64°F 55°F 0.00 in.0.00 in.0.00 in.57%80%99%49°F 7.3 mph 14 mph 22 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
54°F
Clear
56°F
Clear
62°F
Clear
56°F
Clear
52°F
Clear
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:45 AM PST