HomeMy WebLinkAbout2022-01-07FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 1/7/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Sean Ferguson No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Continue vents and water.
2 Troy Rosevear No 00-GENERAL - Continued watering the hydro seed.
- Continued cleaning and repairing BMP's throughout the Site.
- Continued Surveying Curbs and Gutters for Granite.
- Started Excavating to install catch basin and Storm Drain
pipe from the west side of the operations to Storm Pond # 2.
Lots of rock!!!!!!!
- Performed SWPPP site inspection.
3 Troy Rosevear No 20-HEADWORKS AREA - Continued installing PRW to the Odor control and screening
equipment on the south slab of the Headworks.
- Installed 4" SS DI spool to complete the SS lift station
discharge piping to the Headworks.
4 Troy Rosevear No 60-PRODUCT WATER AREA - Leveled and bolted back up the pumps at the outfall and IPR
pump stations.
- Installed pipe supports on the fiberglass tanks
5 Troy Rosevear No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Continued installing the blower lines, defuser piping and
anchors at the BNR Tank. Missing some items from the vendor
which we have ordered.
- Reworked FRP Baffles at the BNR Tank, missing some
hardware which we have ordered.
6 Troy Rosevear No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- Continue vents and water.
- Opened up FBW line so we can repair a leak on the east side
of the SHT.
7 Troy Rosevear No 30-TREATMENT AREA - Installed PRW supports at the MBR tank.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:45 AM PST
MANPOWER LOG 38 Workers | 302.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Knecht's Plumbing & Heating, Inc.3 8.0 24.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Sean Ferguson
2 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Hector Schantz
Created By: Troy Rosevear
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Troy Rosevear
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Brian Elgin
Don Butte
Rick Jenne
Created By: Troy Rosevear
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Mikah Pixley
Created By: Troy Rosevear
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Troy Rosevear
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:45 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Troy Rosevear
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Troy Rosevear
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Troy Rosevear
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Journey Cement Mason
Daniel Sheslingoff
Created By: Troy Rosevear
11 RARIG CONSTRUCTION, INC.2 8.0 16.0
Notes:Trim
Created By: Michael Rarig
12 RARIG CONSTRUCTION, INC.2 7.0 14.0
Notes:Seaming roof
Created By: Michael Rarig
13 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
14 Granite Construction Inc.4 8.0 32.0
Notes:Created By: Brody Gill
38 302.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
1-7-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:45 AM PST
14. Granite Construction Inc.
GCC Daily Report 1.6.22.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Troy Rosevear
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Troy Rosevear
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Troy Rosevear
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Troy Rosevear
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Troy Rosevear
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Troy Rosevear
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:45 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 12:15PM Airgas 9915
Comments:Created By: Monica Weiss
2 12:15PM Ferguson Enterprises, LLC 471-152 A50 RO
Comments:Created By: Monica Weiss
3 12:15PM Ferguson Enterprises, LLC 9656696-2 PVC Tee
Comments:Created By: Monica Weiss
4 12:15PM HD Supply White Cap 45445139 Safety
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.07 Airgas 9915.pdf
2.
2022.01.07 Ferguson 471-152.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:45 AM PST
3.
2022.01.07 Ferguson 9656696-2 PVC tee.pdf
4.
2022.01.07 White Cap 45445139 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 56°F 52°F 0.00 in.0.00 in.0.00 in.75%90%98%50°F 3.2 mph 7 mph 10 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
51°F
Partly Cloudy
51°F
Partly Cloudy
55°F
Cloudy
56°F
Cloudy
55°F
Cloudy
54°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:55:00 AM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:45 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:45 AM PST