HomeMy WebLinkAbout2022-01-08FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Saturday 1/8/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
Continue vents and water.
2 Daniel Ford No 20-HEADWORKS AREA - Fabricate and install 2" PRW in the fine screen area and at the
recirc pump
3 Daniel Ford No 60-PRODUCT WATER AREA - Install the 10" IPR plus the supports
- Spacer bolts for the 10" calcite were installed today
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Installation of anchors and grouting was performed today
- strut was being installed in the washdown area.
5 Daniel Ford No 30-TREATMENT AREA - Installed PRW supports at the MBR tank.
6 Daniel Ford No 50-RO/UV BUILDING - anchoring and work on the supports is ongoing in this
building
MANPOWER LOG 9 Workers | 72.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Hector Schantz
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 09:46 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Orlando Cortez
Rick Jenne
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Apprentice carpenter
Enrique Padila
Created By: Daniel Ford
9 72.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
2 AHERN RENTAL 4.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 09:46 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 United Rental 4.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
4 United Rental 4.0 No 06:15AM
Notes:mini excavator
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 59°F 53°F 0.00 in.0.00 in.0.00 in.59%74%95%45°F 7.7 mph 13 mph 26 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
50°F
Clear
51°F
Clear
58°F
Clear
59°F
Clear
55°F
Clear
54°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:15:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 3 of 3 Printed on 1/24/2023 at 09:46 AM PST