HomeMy WebLinkAbout2022-01-11FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 1/11/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Continued cleaning and repairing BMP's throughout the Site.
-The excavation for the DI and drain pipe west of the Opps
building continues. We are digging through lots of rocks and
pipes running across our excavation
- We were cleaning mud out of the swales all over the job
- The 3" PRW water line test passed at 125 lbs of pressure
- Spoils from Granite are being removed
-The FBW line was being worked on near the the dewatering
pad.
- The 4" PRW pipe just east of the lower head works pad was
encased in concrete.
- 2 small equipment pads were placed and finished near the
product water tank today.
2 Daniel Ford No 20-HEADWORKS AREA - We installed the PRW hose bib
-The bushing for the headworks PRW line was installed.
3 Daniel Ford No 60-PRODUCT WATER AREA - Painting of the outfall pipes continues
- We are working on some anchors and pipe supports
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Continued installing the blower lines, defuser piping and
anchors at the BNR Tank. Missing some items from the vendor
which we have ordered.
- Reworked FRP Baffles at the BNR Tank, missing some
hardware which we have ordered.
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- the anchoring and grouting for the MBR piping continues.
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:49 AM PST
MANPOWER LOG 36 Workers | 292.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.2 8.0 16.0
Notes:Created By: Brody Gill
2 RARIG CONSTRUCTION, INC.4 8.0 32.0
Notes:Trim
Created By: Michael Rarig
3 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Johnathan Torres
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Raul Velasquez
Mikah Pixley
Enrique Padilla
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:49 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
11 Parada Painting Inc.2 10.0 20.0 12-NORTH -
PIPING
Notes:Primer Pipe
Created By: Monica Weiss
12 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
36 292.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:49 AM PST
1. Granite Construction Inc.
GCC Daily Report 1.10.22.pdf
11. Parada Painting Inc.
01.11 DFR PARADA.pdf
12. ELECTRICRAFT, INC.
1-11-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:49 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:15PM CalPortland Pipe Encasement
Comments:Created By: Monica Weiss
2 01:15PM Harrington Industrial Plastics
LLC
RO A50 CPVC
Comments:Created By: Monica Weiss
3 01:15PM Harrington Industrial Plastics
LLC
004L4223-6 RO/ CPVC
Comments:Created By: Monica Weiss
4 01:15PM Miner's Ace Hardware 727251 Parts
Comments:Created By: Monica Weiss
5 01:15PM Morro Gas FUEL
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:49 AM PST
1.
2022.01.11 Calportland Pipe Encase.pdf
2.
2022.01.11 Harrington RO A50 CPVC.pdf
3.
2022.01.11 Harrington 004l4223-6.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:49 AM PST
4.
2022.01.11 Miners 727251 Parts.pdf
5.
2022.01.11 Morro Gas Fuel.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
52°F 71°F 60°F 0.00 in.0.00 in.0.00 in.24%37%51%33°F 9.6 mph 14 mph 20 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
53°F
Clear
57°F
Clear
64°F
Clear
72°F
Clear
64°F
Clear
60°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:40:00 AM No
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:49 AM PST