HomeMy WebLinkAbout2022-01-12FBV Morro Bay Joint Venture 2999 Oak Rd. #490 Walnut Creek , California 94597 Project: 471 - Morro Bay Water Reclamation Facility  Morro Bay , California 93442 Daily Log: Wednesday 1/12/2022    NOTES LOG    No.Created By Issue?Location Comments   1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed. - Continued cleaning and repairing BMP's throughout the Site. -The excavation for the DI and drain pipe west of the Opps building continues. We are digging through lots of rocks and pipes running across our excavation - We were cleaning mud out of the swales all over the job - The 6" FBW water line test passed at 125 lbs of pressure - Spoils from Granite are being removed - The West side of the opps building was - We are hunting a leak in the 3" PW line between the chemical and Ro building 2 Daniel Ford No 20-HEADWORKS AREA We set up and placed concrete in a equipment pad under the 2 WWR pipes to the east of the head works pad. 3 Daniel Ford No 60-PRODUCT WATER AREA - Painting of the outfall pipes continues - We are working on some anchors and pipe supports 4 Daniel Ford No 30-TREATMENT AREA>31- Treatment Area - BNR Basins - We are working on the 3" PRW line for the BNR tank 5 Daniel Ford No 30-TREATMENT AREA>32- Treatment Area - MBR System - the anchoring and grouting for the MBR piping continues. 6 Daniel Ford No 50-RO/UV BUILDING Fab 8" PVC ine was being fabricated   MANPOWER LOG 40 Workers  |   335.5 Man Hours No.Contact/Company Workers # Hours Man Hours Location     1 Granite Construction Inc.5 8.0 40.0     Notes:Created By:  Brody Gill     FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 09:49 AM PST        No.Contact/Company Workers # Hours Man Hours Location     2 Granite Construction Inc.2 9.0 18.0     Notes:Created By:  Brody Gill   3 Granite Construction Inc.1 9.5 9.5     Notes:Created By:  Brody Gill   4 RARIG CONSTRUCTION, INC.4 8.0 32.0     Notes:Trim and ridge cap Created By:  Michael Rarig    5 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL     Notes:JOURNEYMAN LABORERS Manny Hernandez Estaban zamudio Charlie Gonzales Angel Diaz Martin Castillo Created By:  Daniel Ford    6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:LABORER APPRENTICE Teddy Maldonado Created By:  Daniel Ford    7 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL     Notes:JOURNEYMAN CARPENTERS Coy Brite Brian Elgin Rick Jenne Orlando Cortez Created By:  Daniel Ford    8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:CARPENTER APPRENTICE Raul Velasquez Enrique Padilla Created By:  Daniel Ford      FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 09:49 AM PST        No.Contact/Company Workers # Hours Man Hours Location     9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:Certified Welder Pipefitter Rick Dayton Created By:  Daniel Ford    10 J.R. Filanc Construction Company, Inc.2 11.0 22.0 00-GENERAL     Notes:APPRENTICE CEMENT MASON Adolfo Campoverde Samuel Rannals Created By:  Daniel Ford    11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:SUPERINTENDENT Troy Rosevear Created By:  Daniel Ford    12 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:Operator Trevor Hernandez Kyle Brooking Created By:  Daniel Ford    13 1 11.0 11.0     Notes:Carpenter Forman Phil Lacey Created By:  Daniel Ford    14 1 7.0 7.0     Notes:Labor Forman Ricardo Belmontez Created By:  Daniel Ford    15 Parada Painting Inc.2 10.0 20.0 12-NORTH - PIPING     Notes:Primer Created By:  Monica Weiss    16 ELECTRICRAFT, INC.5 8.0 40.0     Notes:Created By:  Rick Howland      40  335.5    Manpower Log's Attachments:    FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 09:49 AM PST        3.  Granite Construction Inc.  GCC Daily Report 1.11.22.pdf 15.  Parada Painting Inc.  01.12 DFR PARADA.pdf 16.  ELECTRICRAFT, INC.    1-12-2022 Daily Report.xls     EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 United Rental 8.0 0.0 No   06:05AM  00-GENERAL  Notes:18000 pound mini excavator Created By: Daniel Ford   2 United Rental 8.0 No   12:20PM  00-GENERAL  Notes:Scissor lift Created By: Daniel Ford   3 AHERN RENTAL 8.0 No   05:40AM    Notes:Scissor lift Created By: Daniel Ford     FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 09:49 AM PST          EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   4 United Rental 8.0 No   03:05PM  00-GENERAL  Notes:24k generator Created By: Daniel Ford   5 AHERN RENTAL 8.0 No   05:40AM    Notes:45' ariel lift Created By: Daniel Ford   6 United Rental 8.0 No   02:00PM  00-GENERAL  Notes:Telescoping Forklift Created By: Daniel Ford     DELIVERY LOG No.Time Delivery From Tracking Number Contents   1 01:30PM   Ferguson Enterprises, LLC 9702852 158.1    Comments:F REQ As Built Created By: Monica Weiss 2 01:30PM   CalPortland P#87 Equipment Pad Area 20    Comments:Created By: Monica Weiss Delivery Log's Attachments: 1.  2022.01.12 Ferguson 158.1 9702852.pdf   FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 09:49 AM PST        2.  2022.01.12 Calportland P#87 EqPd A20.pdf   WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 54°F 66°F 59°F 0.00 in.0.00 in.0.00 in.31%40%57%35°F 4.7 mph 13 mph 19 mph   DAILY SNAPSHOT 06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM Clear   55°F Clear   58°F Partly Cloudy   64°F Partly Cloudy   65°F Cloudy   60°F Cloudy   56°F   OBSERVED WEATHER CONDITIONS No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea   1 05:50:00 AM No       By  Date  Copies To   FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 09:49 AM PST