HomeMy WebLinkAbout2022-01-12FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 1/12/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Continued cleaning and repairing BMP's throughout the Site.
-The excavation for the DI and drain pipe west of the Opps
building continues. We are digging through lots of rocks and
pipes running across our excavation
- We were cleaning mud out of the swales all over the job
- The 6" FBW water line test passed at 125 lbs of pressure
- Spoils from Granite are being removed
- The West side of the opps building was
- We are hunting a leak in the 3" PW line between the chemical
and Ro building
2 Daniel Ford No 20-HEADWORKS AREA We set up and placed concrete in a equipment pad under the
2 WWR pipes to the east of the head works pad.
3 Daniel Ford No 60-PRODUCT WATER AREA - Painting of the outfall pipes continues
- We are working on some anchors and pipe supports
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are working on the 3" PRW line for the BNR tank
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- the anchoring and grouting for the MBR piping continues.
6 Daniel Ford No 50-RO/UV BUILDING Fab 8" PVC ine was being fabricated
MANPOWER LOG 40 Workers | 335.5 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.5 8.0 40.0
Notes:Created By: Brody Gill
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 09:49 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 Granite Construction Inc.2 9.0 18.0
Notes:Created By: Brody Gill
3 Granite Construction Inc.1 9.5 9.5
Notes:Created By: Brody Gill
4 RARIG CONSTRUCTION, INC.4 8.0 32.0
Notes:Trim and ridge cap
Created By: Michael Rarig
5 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Raul Velasquez
Enrique Padilla
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 09:49 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.2 11.0 22.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
13 1 11.0 11.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
14 1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
15 Parada Painting Inc.2 10.0 20.0 12-NORTH -
PIPING
Notes:Primer
Created By: Monica Weiss
16 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
40 335.5
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 09:49 AM PST
3. Granite Construction Inc.
GCC Daily Report 1.11.22.pdf
15. Parada Painting Inc.
01.12 DFR PARADA.pdf
16. ELECTRICRAFT, INC.
1-12-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 09:49 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:30PM Ferguson Enterprises, LLC 9702852 158.1
Comments:F REQ As Built
Created By: Monica Weiss
2 01:30PM CalPortland P#87 Equipment Pad Area 20
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.12 Ferguson 158.1 9702852.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 09:49 AM PST
2.
2022.01.12 Calportland P#87 EqPd A20.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 66°F 59°F 0.00 in.0.00 in.0.00 in.31%40%57%35°F 4.7 mph 13 mph 19 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
55°F
Clear
58°F
Partly Cloudy
64°F
Partly Cloudy
65°F
Cloudy
60°F
Cloudy
56°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 09:49 AM PST