1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- The 2" PVC at the vacor washdown area for clean outs and
the hose bibs was being installed.
- We continued with the pipe testing and filled the PRW line
- The FBW line has passed testing and is being backfilled
- Near the opps building the basin and piping was backfilled
- Just west of the product water tank the PW line was dug up
and we discovered a leak and are going to instal an shutoff
valve
- The level spreaders area being mucked out and backfilled
- We are breaking out the concrete next to the RO Feed tank to
insta a yard hydrant
2 Daniel Ford No 20-HEADWORKS AREA -We stripped the equipment pad and cleaned everything up.
-Some work continues for the anchoring and pipe supports
3 Daniel Ford No 60-PRODUCT WATER AREA - Painting of the outfall pipes continues
- We are working on some anchors and pipe supports
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We are working on the 3" PRW line for the BNR tank
- The work on al the diffusers continues
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- the anchoring and grouting for the MBR piping continues.
6 Daniel Ford No 50-RO/UV BUILDING Fab 8" PVC ine was being fabricated
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:50 AM PST
MANPOWER LOG 42 Workers | 341.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Granite Construction Inc.9 8.0 72.0
Notes:Created By: Brody Gill
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Teddy Maldonado
Jonathan Torres
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Raul Velasquez
Micha Pixley
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:50 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.1 11.0 11.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 11.0 11.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
12 RARIG CONSTRUCTION, INC.4 8.0 32.0
Notes:Trim and downspouts
Created By: Michael Rarig
13 ELECTRICRAFT, INC.7 8.0 56.0
Notes:Created By: Rick Howland
42 341.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:50 AM PST
1. Granite Construction Inc.
GCC Daily Report 1.12.22.pdf
13. ELECTRICRAFT, INC.
1-13-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:50 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 01:50PM Miner's Ace Hardware 727459 727176 PVC Cement
Comments:Created By: Monica Weiss
2 01:50PM JB DEWAR, INC 190278 FUEL
Comments:Created By: Monica Weiss
3 01:50PM Harrington Industrial Plastics
LLC
CPVC Valves
Comments:Created By: Monica Weiss
4 01:50PM Airgas 8470,5621,5474 Safety and Welding Supplies
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.01.13 Miners 727459 727176 .pdf
2.
2022.01.13 JB Dewar 190278.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:50 AM PST
3.
2022.01.13 Harrington CPVC Valves.pdf
4.
2022.01.13 Airgas 5621.pdf
2022.01.13 Airgas 5474 Backorder.pdf
2022.01.13 Airgas 8470.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 65°F 59°F 0.00 in.0.00 in.0.00 in.41%49%67%40°F 4.8 mph 8 mph 16 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:50 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
55°F
Cloudy
56°F
Cloudy
62°F
Partly Cloudy
65°F
Cloudy
63°F
Cloudy
61°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No