HomeMy WebLinkAbout2022-01-18FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Tuesday 1/18/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- The 2" PVC at the vacor washdown area for clean outs and
the hose bibs was being installed.
- We continued with the pipe testing and filled the PRW line
- We excavated and backfill the 4" PRW line
- We "As built" everything that is going to be under the asphalt
- We removed the excess concrete near the entrance at the
frog wall.
- The Tape covering all the exterior drains has been removed.
2 Daniel Ford No 20-HEADWORKS AREA -We stripped the equipment pad and cleaned everything up.
-Some work continues for the anchoring and pipe supports
- The rebar that set the height for the Headworks skids was
removed today.
- The PS at the fine screens and the 1" SS pipe fittings were
installed and welded.
3 Daniel Ford No 60-PRODUCT WATER AREA - Painting of the outfall pipes continues
- We are working on some anchors and pipe supports
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We installed the PHS at the scum pumps
5 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The Air compressors and and the air tank were set and
anchored.
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- We removed the blind fange from the RAZ line, wire wheeled
the surface, and painted the surface with Bitmastic paint.
7 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The anchors at the dewatering continued to be installed.
- The PRW in this area was being fabricated and installed
_ The 2" PVC for pumps is being worked on
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 09:52 AM PST
MANPOWER LOG 32 Workers | 258.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Teddy Maldanado
Ben Marquez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 11.0 11.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 09:52 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Genera Forman
Daniel Ford
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
12 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
32 258.0
Manpower Log's Attachments:
12. ELECTRICRAFT, INC.
1-18-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 09:52 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:10AM Fastenal 471-155 A30 Bolts
Comments:Created By: Monica Weiss
2 07:10AM Custom Conveyor Dewatering Conveyor A72
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 09:52 AM PST
1.
2022.01.18 Fastenal 471-155_A30.pdf
2.
2022.01.18 Custom Conveyor Dewatering.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 57°F 53°F 0.00 in.0.04 in.0.05 in.83%88%94%50°F 4.0 mph 9 mph 14 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
52°F
Partly Cloudy
54°F
Clear
57°F
Clear
56°F
Clear
54°F
Clear
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:45:00 AM No
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 09:52 AM PST
By Date Copies To