HomeMy WebLinkAbout2022-01-19FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 1/19/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We continued mucking out the concrete v ditches
- The Electrical vaults were being cleaned out
- We are cleaning up all the concrete spoils near the entrance
and the frog wall
- We were backfilling and moving dirt around the job
-The PW line was repaired
- We continue going through gages and instruments.
We worked on the level spreaders.
2 Daniel Ford No 20-HEADWORKS AREA -The bolt up is on going for the upper headworks equipment.
A list was created of al missing bolts and components.
-The Fine screens are being anchored
- The Handrail was gone though and a list was created of
broken and missing components
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We installed the PHS at the scum pumps
4 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The gauge for the Air tank was installed
5 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The anchors at the dewatering continued to be installed.
- The PRW in this area was being fabricated and installed
_ The 2" PVC for pumps is being worked on
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:52 AM PST
MANPOWER LOG 31 Workers | 250.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Teddy Maldanado
Ben Marquez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Micha Pixley
Enrique Padilla
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 11.0 11.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:52 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Genera Forman
Daniel Ford
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Forman
Phil Lacey
Created By: Daniel Ford
13 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
31 250.0
Manpower Log's Attachments:
13. ELECTRICRAFT, INC.
1-19-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:52 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:25AM Capital Flow 471-156 BNR Blower SS
Comments:Created By: Monica Weiss
2 07:25AM Ferguson Enterprises, LLC 9707398 A20 Bolts Gasket
Comments:Created By: Monica Weiss
3 07:25AM Ferguson Enterprises, LLC 9715632 FREQ TESTING
Comments:Created By: Monica Weiss
4 07:25AM Miner's Ace Hardware 727826 gas can
Comments:Created By: Monica Weiss
5 07:25AM Morro Gas Fuel for Truck
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:52 AM PST
Delivery Log's Attachments:
1.
2022.01.19 Capflo 471156 BNR Blower SS.pdf
2.
2022.01.19 Ferguson 9707398 Bolts gasket A20.pdf
3.
2022.01.19 Ferguson 9715632 Freq Test.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:52 AM PST
4.
2022.01.19 Miners 727826.pdf
5.
2022.01.19 Morro Gas.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 63°F 54°F 0.00 in.0.00 in.0.04 in.54%77%97%46°F 4.6 mph 9 mph 14 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
46°F
Clear
50°F
Clear
62°F
Clear
59°F
Clear
60°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 02:00:00 PM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:52 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:52 AM PST