HomeMy WebLinkAbout2022-01-22FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Saturday 1/22/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL
2 Daniel Ford No 20-HEADWORKS AREA -The bolt up is on going for the upper headworks equipment.
A list was created of al missing bolts and components.
-The Fine screens are being anchored as well as the pipe
supports for the WWS line
- We are sacking and patching everything in the Headworks
area
- Forms are set up for pads under the WWS 14" 90's and under
3 foul air components
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- We were fabricating all the 5 inch reducers for the SS blower
piping
4 Daniel Ford No 60-PRODUCT WATER
AREA>61-Product Water
Area - Calcite Contactor
-the Air vacs area being installed.
-We fabricated and are installi ng the drains in this area
5 Daniel Ford No 60-PRODUCT WATER
AREA>63-Product Water -
IPR Product Water Pump
Station
- The 6" FLG adapter for the IPR line is being installed
MANPOWER LOG 16 Workers | 130.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Angel Diaz
Martin Castillo
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 09:53 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Teddy Maldanado
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Jason Hawthorne
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Pablo Campoverde
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:SUPERINTENDENT
Troy Rosevear
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 09:53 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Genera Forman
Daniel Ford
Created By: Daniel Ford
16 130.0
Manpower Log's Attachments:
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
49°F 65°F 56°F 0.00 in.0.00 in.0.00 in.33%48%67%36°F 6.0 mph 10 mph 16 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
54°F
Partly Cloudy
56°F
Partly Cloudy
64°F
Clear
61°F
Clear
57°F
Clear
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:25:00 AM No