Daily Log: Thursday 1/27/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Job site clean up
- cleaned mud out v diches
- excavation for curb and gutter all over the job
-
2 Daniel Ford No 20-HEADWORKS AREA - Fab and install Drains and supports
-
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Allied Steel continues with their handrail install.
- Change the pan cakes for testing on the 12" overflow and the
18" lines
- Install the PSH gages for the filtration pump #2
- Install the level transmitter for the RO feed tanks (both 1 and
2)
- We started the fabrication for the 3" drains (RO Feed Tank)
- Start Fabricating the drain supports and test the RO 12" PVC
line.
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Working on diffuser piping east & west
- Work continues on the FRP baffles
- The sidewalk and landings for the northern staircase on this
building is being laid out
5 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Worked on walk way an stariecase
- Anchored down pipe suppers an staircase strucure
- Cleaned up area
- weld suporets
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- fab & install 2" PRW at dewatering
7 Daniel Ford No 50-RO/UV BUILDING - Some work on pipe supports continue
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:55 AM PST
MANPOWER LOG 27 Workers | 217.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rias Lopez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Pablo Campoverde
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:55 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
9 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
27 217.0
Manpower Log's Attachments:
9. ELECTRICRAFT, INC.
1-27-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:55 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:10AM Capital Flow 471-167 SS Tube
Comments:Created By: Monica Weiss
2 08:10AM Capital Flow 471-167 Galvinized bushings
Comments:Created By: Monica Weiss
3 08:10AM Harrington Industrial Plastics
LLC
4L4750-02 Inj Quills Valve
Comments:Created By: Monica Weiss
4 08:10AM Harrington Industrial Plastics
LLC
471-159 Strut
Comments:Created By: Monica Weiss
5 08:10AM THE HOME DEPOT Sheds
Comments:Created By: Monica Weiss
6 08:10AM Miner's Ace Hardware 728559 BNR Taps
Comments:Created By: Monica Weiss
7 08:10AM Ryan Herco Apollo Valves
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:55 AM PST
1.
2022.01.27 Capflo 471-167 SS Tube.pdf
2.
2022.01.27 Capflo 471-167 .pdf
3.
2022.01.27 Harrington 4l4750-2 MR135 Inj Q Valve.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:55 AM PST
4.
2022.01.27 Harrington 471-159 Strut.pdf
5.
2022.01.27 Home Depot 3 Sheds.pdf
6.
2022.01.27 Miners 728559 BNR Taps.pdf
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:55 AM PST
7.
2022.01.27 Ryan Herco Apollo Valves.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 61°F 55°F 0.00 in.0.00 in.0.00 in.40%56%77%39°F 4.7 mph 7 mph 13 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
53°F
Clear
55°F
Clear
61°F
Clear
58°F
Clear
56°F
Clear
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:05:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 09:55 AM PST