Daily Log: Friday 1/28/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Job site clean up
- cleaned mud out v diches
- excavation for curb and gutter all over the job (sub grade
and moving the spoils)
- We picked up trash from al over the job site.
- Dust control
2 Daniel Ford No 20-HEADWORKS AREA - Fab and install Drains and supports
- Sacking and patching continues
- We are installing the 4" PVC 90's for the drain
- The two pads were laid out and formed for the stair landings
on the east and west side of the headworks.
- we laid out a potential spot for the sample box pad
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Allied Steel continues with their handrail install.
- We started the fabrication for the 3" drains (RO Feed Tank)
- Start Fabricating the drain supports and test the RO 12" PVC
line.
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Working on diffuser piping east & west
- Work continues on the FRP baffles
- The sidewalk and landings for the northern staircase on this
building is formed.
- Spray nozzle layout and strut installation is in progress.
- The 2" PRW line for the BNR tank is being installed.
- Drilled and installed the 6" saddle clamp in pump
5 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Worked on walk way and staircase
- Anchored down pipe suppers an staircase structure
- Cleaned up area
- weld supports
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 09:56 AM PST
NOTES LOG
No.Created By Issue?Location Comments
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- fab & install 2" PRW at dewatering
7 Daniel Ford No 50-RO/UV BUILDING - Some work on pipe supports continue
MANPOWER LOG 26 Workers | 209.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rias Lopez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 09:56 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Pablo Campoverde
Raul Velasquez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
26 209.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
1-28-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 09:56 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
50°F 61°F 53°F 0.00 in.0.00 in.0.00 in.29%56%81%39°F 2.7 mph 5 mph 8 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
52°F
Clear
52°F
Clear
58°F
Clear
59°F
Clear
52°F
Cloudy
51°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:15:00 AM No