HomeMy WebLinkAbout2022-01-29FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Saturday 1/29/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Instruments were installed
- We water tested the filtration line in the slab
- supports were anchored
2 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Working on diffuser piping east & west
- Work continues on the FRP baffles
- The sidewalk and landings for the northern staircase on this
building is formed.
- Spray nozzle layout and strut installation is in progress.
- The 2" PRW line for the BNR tank is being installed.
- Drilled and installed the 6" saddle clamp in pump
3 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- Cleaned up area
- We grouted in the safe filter
4 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- fab & install 2" PRW at dewatering
5 Daniel Ford No 50-RO/UV BUILDING - Some work on pipe supports continue
MANPOWER LOG 14 Workers | 112.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Angel Diaz
Martin Castillo
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 09:56 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Pablo Campoverde
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
14 112.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 09:56 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
54°F 66°F 58°F 0.00 in.0.00 in.0.00 in.23%34%43%30°F 7.1 mph 12 mph 18 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Cloudy
55°F
Cloudy
55°F
Partly Cloudy
62°F
Partly Cloudy
67°F
Clear
60°F
Clear
59°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 03:30:00 PM No
By Date Copies To