Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 1/31/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Job site clean up
- cleaned mud out v diches
- excavation for curb and gutter all over the job (sub grade
and moving the spoils)
- We picked up trash from al over the job site.
- Dust control
- Superior Gunite we working on the concrete swales at the
soi slip area and in the ravine
2 Daniel Ford No 20-HEADWORKS AREA - We installed the ph sensor for the foul air
- The two pads were laid out and formed for the stair
landings on the east and west side of the headworks.
- we laid out a potential spot for the sample box pad and
summited it to the design team
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Allied Steel continues with their handrail install.
- We started the fabrication for the 3" drains (RO Feed Tank)
- Start Fabricating the drain supports and test the RO 12" PVC
line.
- The Cassette filtration and ejector were installed for the
northern line today
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- Working on diffuser piping east & west
- Work continues on the FRP baffles
- Spray nozzle layout and strut installation is in progress.
- The 2" PRW line for the BNR tank is being installed.
_ We connected all the SS blower piping to the diffusers on
the west side of the tank
5 Daniel Ford No 50-RO/UV BUILDING - Some work on pipe supports continue
6 Daniel Ford No 60-PRODUCT WATER AREA - We went back and tightened al the bots for area 60
7 Monica Weiss No 00-GENERAL Storm Water Training
FBV Morro Bay Joint Venture Page 1 of 5 Printed on 1/24/2023 at 09:56 AM PST
Notes Log's Attachments:
7.
2022.01.31 SWT.pdf
MANPOWER LOG 22 Workers | 171.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 5 Printed on 1/24/2023 at 09:56 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
9 Superior Gunite 3 6.0 18.0
Notes:Install Meshwire
Created By: Monica Weiss
22 171.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 5 Printed on 1/24/2023 at 09:56 AM PST
9. Superior Gunite
01.31 DFR Superior.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 5 Printed on 1/24/2023 at 09:56 AM PST
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
47°F 62°F 55°F 0.00 in.0.00 in.0.00 in.38%51%80%38°F 7.3 mph 10 mph 15 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
50°F
Partly Cloudy
53°F
Cloudy
63°F
Cloudy
62°F
Cloudy
59°F
Partly Cloudy
57°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:15:00 AM No
By Date Copies To