No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Backfilling and hauling dirt to the ravine
- A couple hours on the level spreaders
- excavation for curb and gutter all over the job (sub grade
and moving the spoils)
- Spoils were dozed up and spoils from superior were dealt
with
2 Daniel Ford No 20-HEADWORKS AREA - We grouted some equipment at the headworks
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are drilling and installing the brackets for the metal tanks
- Work on the instrumentation continues
- Start Fabricating the drain supports and test the RO 12" PVC
line.
- The Cassette filtration and ejector were installed for the
northern line today
- The install for the AIR comp piping on the cassette is ongoing
- Install drain valves for the scum and WAS pumps
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The 2" PRW line for the BNR tank is being installed.
- We connected all the SS blower piping to the diffusers on the
East side of the tank
- We are welding the 5" SS flanges for the BNR air lines
- The diffuser piping continues
- We modified
MANPOWER LOG 35 Workers | 285.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Moldanado
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
9 ELECTRICRAFT, INC.8 8.0 64.0
Notes:Created By: Rick Howland
10 Parada Painting Inc.2 10.0 20.0 60-PRODUCT
WATER AREA>64-
Product Water -
Outfall Pump
Station
Notes:Created By: Monica Weiss
11 Allied Steel Co., Inc.3 8.0 24.0
Notes:MBR Tank
Created By: Monica Weiss
35 285.0
Manpower Log's Attachments:
9. ELECTRICRAFT, INC.
2-3-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:58 AM PST
10. Parada Painting Inc.
02.03 DFR PARADA.pdf
11. Allied Steel Co., Inc.
2022.02.03 Allied DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:58 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 10:35AM Capital Flow SS Fittings
Comments:Created By: Monica Weiss
2 10:35AM Capital Flow SS Tubing
Comments:Created By: Monica Weiss
3 10:35AM Ferguson Enterprises, LLC 36in SS
Comments:Created By: Monica Weiss
4 10:35AM Ferguson Enterprises, LLC Romac Saddle
Comments:Created By: Monica Weiss
5 10:35AM Miner's Ace Hardware PVC 729090
Comments:Created By: Monica Weiss
6 10:35AM Sitech Trimble Stand
Comments:Created By: Monica Weiss
7 10:35AM Ferguson Enterprises, LLC Zephyr Fume Hood
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:58 AM PST
1.
2022.02.03 Capflo SS Fittings.pdf
2.
2022.02.03 Capflo SS Tube.pdf
3.
2022.02.03 Ferguson 36in SS.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:58 AM PST
4.
2022.02.03 Ferguson Romac Saddle.pdf
5.
2022.02.03 Miners PVC 729090.pdf
6.
2022.02.03 Sitech Trimble Stand.pdf
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:58 AM PST
7.
2022.02.03 Zephyr Fume Hood.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
47°F 61°F 52°F 0.00 in.0.00 in.0.00 in.25%53%83%34°F 5.2 mph 9 mph 15 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
47°F
Clear
51°F
Clear
62°F
Partly Cloudy
57°F
Clear
54°F
Clear
49°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:15:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 8 of 8 Printed on 1/24/2023 at 09:58 AM PST