HomeMy WebLinkAbout2022-02-04FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 2/4/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are removing the hay from the v ditch
- We picked up trash all over the fence line.
- excavation for curb and gutter all over the job (sub grade
and moving the spoils)
- Spoils were dozed up and spoils from superior were dealt
with
- Pipe testing for the PRW continues
2 Daniel Ford No 20-HEADWORKS AREA - We set up 2 slabs for the 2 stairs off the headworks and for
the sample box.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are drilling and installing the brackets for the metal tanks
- Work on the instrumentation continues
- We install 12" saddles for the RO feed tanks on the 12" PVC
line
- The 3/4" air was installed
- We installed the 14" supports
- The 2" CPVC containment on the cassette tank continues
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The Diffusers continue to be worked on
- We connected all the SS blower piping to the diffusers on the
East side of the tank
- We are welding the 5" SS flanges for the BNR air lines
5 Daniel Ford No 60-PRODUCT WATER AREA We set up a 4'x4' slap for the 20" overflow off the outfall
balance tank.
FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 09:58 AM PST
MANPOWER LOG 31 Workers | 237.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.7 8.0 56.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Moldanado
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 09:58 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 Parada Painting Inc.2 2.0 4.0 60-PRODUCT
WATER AREA
Notes:Created By: Monica Weiss
31 237.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
2-4-2022 Daily Report.xls
10. Parada Painting Inc.
02.04 DFR PARADA.pdf
FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 09:58 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 10:50AM Spraying Systems BNR A31 Nozzles
Comments:Created By: Monica Weiss
2 10:50AM Parada Painting Inc.Tnemec Paint
Comments:Created By: Monica Weiss
3 10:50AM PACIFIC COAST BOLT CORP 471-180 A32
Comments:Created By: Monica Weiss
4 10:50AM Morro Gas Fuel
Comments:Created By: Monica Weiss
5 10:50AM Harrington Industrial Plastics
LLC
471-182 4L5053-3
Comments:Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 09:58 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
6 10:50AM Fastenal A31
Comments:Created By: Monica Weiss
7 10:50AM Capital Flow Die electric Union
Comments:Created By: Monica Weiss
8 10:50AM Airgas 2842 Argon
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.02.04 Spraying Systems BNR A31.pdf
2.
2022.02.04 Parada Paint.pdf
FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 09:58 AM PST
3.
2022.02.04 Pac Coast Bolt 471-180 A32.pdf
4.
2022.02.04 Morro Gas.pdf
5.
2022.02.04 Harrington 471-182 4L5053-3.pdf
FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 09:58 AM PST
6.
2022.02.04 Fastenal A31.pdf
7.
2022.02.04 Capflo Dieelectric Union.pdf
8.
2022.02.04 Airgas 2842 Argon.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
44°F 63°F 53°F 0.00 in.0.00 in.0.00 in.44%56%76%37°F 6.0 mph 11 mph 21 mph
FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 09:58 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
48°F
Clear
51°F
Clear
60°F
Clear
62°F
Clear
55°F
Clear
54°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:05:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 8 of 8 Printed on 1/24/2023 at 09:58 AM PST