HomeMy WebLinkAbout2022-02-07FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Monday 2/7/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are removing the hay from the v ditch
- Spreading hay at the frog wall
- excavation for curb and gutter all over the job (sub grade
and moving the spoils)
- Work continues at the Level spreaders
- Pipe testing for the PRW continues
- Curb and gutters excavation continues
- 12" PVC was installed at the declor pad
2 Daniel Ford No 20-HEADWORKS AREA -We placed concrete for the 2 stairs off the headworks and for
the sample box as well as 2 equipment pads.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are drilling and installing the brackets for the metal tanks
- Work on the instrumentation continues
- We install 12" saddles for the RO feed tanks on the 12" PVC
line
- The 3/4" air was installed
- We installed the 14" supports
- The 2" CPVC containment on the cassette tank continues
- We placed concrete for a small landing at the Stairs at the
north end of the MBR/BNR area.
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The Diffusers continue to be worked on
- We connected all the SS blower piping to the diffusers on the
East side of the tank
- The FRP baffles are being bolted up
5 Daniel Ford No 60-PRODUCT WATER AREA Placed concrete in a 4'x4' slap for the 20" overflow off the
outfall balance tank.
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 09:59 AM PST
MANPOWER LOG 31 Workers | 249.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 RARIG CONSTRUCTION, INC.4 8.0 32.0 90-CHEMICAL
FACILITY
Notes:Roofing
Created By: Michael Rarig
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Moldanado
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 09:59 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
31 249.0
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
2-7-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 09:59 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:00AM Harrington Industrial Plastics
LLC
471-183
Comments:Created By: Monica Weiss
2 11:00AM HD Supply White Cap Grade Tape
Comments:Created By: Monica Weiss
3 11:00AM TRI STAR INDUSTRIAL LLC Pipe Supports
Comments:Created By: Monica Weiss
4 11:00AM Harrington Industrial Plastics
LLC
SS Bushings
Comments:Created By: Monica Weiss
5 11:00AM Harrington Industrial Plastics
LLC
A50 4L5053-2
Comments:Created By: Monica Weiss
6 11:00AM Ferguson Enterprises, LLC Angle Valves
Comments:Created By: Monica Weiss
7 11:00AM CalPortland
Comments:Stair Landing
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 09:59 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.02.07 Harrington Clamps 471-183.pdf
2.
2022.02.07 White Cap Grade Tape.pdf
3.
2022.02.07 Tristar Pipe Supports MBR A32.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 09:59 AM PST
4.
2022.02.07 Harrington 471-183 Bushing SS.pdf
5.
2022.02.07 Harrington 4L5053-2 A50.pdf
6.
2022.02.07 Ferguson Angle Valve.pdf
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 09:59 AM PST
7.
2022.02.07 Calportland Pipe Support Stair Landing.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
44°F 58°F 51°F 0.00 in.0.00 in.0.00 in.51%71%88%42°F 2.6 mph 5 mph 9 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
45°F
Clear
51°F
Clear
56°F
Clear
59°F
Clear
57°F
Clear
50°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 11:35:00 AM No
By Date Copies To