HomeMy WebLinkAbout2022-02-09FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 2/9/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are removing the hay from the v ditch
- We took the yard truck to Santa Maria Tire to get new tires
- We are digging, detecting, and repairing leaks for the PW line
near buildings 17 and 15
- Work continues on the level spreaders
2 Daniel Ford No 20-HEADWORKS AREA - We are installing the pipe supports for the 6" line on the
outside of safe filter box.
- We removing the forms for the pipe support pads at the foul
air
- The pipe supports for the WWS line is in progress.
- 1 1/2 angel valves for the hose bibs
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed
- We are working on the relief and rupture discs for the was
and scum
- The 2" blind at to RO feed tank
- Instlal the bolts at the PRW pumps
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The Diffusers continue to be worked on
- We connected all the SS blower piping to the diffusers on the
East side of the tank
- The FRP baffles are being bolted up
5 Daniel Ford No 60-PRODUCT WATER AREA Placed concrete in a 4'x4' slap for the 20" overflow off the
outfall balance tank.
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:00 AM PST
MANPOWER LOG 35 Workers | 278.5 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 RARIG CONSTRUCTION, INC.5 7.5 37.5 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Roofing and trim
Created By: Michael Rarig
2 J.R. Filanc Construction Company, Inc.7 8.0 56.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Daniel Waddle
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:00 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
35 278.5
Manpower Log's Attachments:
10. ELECTRICRAFT, INC.
2-9-2022 Daily Report.xls
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:00 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 11:25AM Ferguson Enterprises, LLC 471-176 As Builts
Comments:Created By: Monica Weiss
2 11:25AM Harrington Industrial Plastics
LLC
471-182 PVC
Comments:Created By: Monica Weiss
3 11:25AM Harrington Industrial Plastics
LLC
MR137 A60
Comments:Created By: Monica Weiss
4 11:25AM JB DEWAR, INC 19462
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:00 AM PST
1.
2022.02.09 Ferguson 471-176 A30 AsBlt.pdf
2.
2022.02.09 Harrington 471-182 PVC Pipe.pdf
3.
2022.02.09 Harrington MR137 A60.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:00 AM PST
4.
2022.02.09 JB Dewar 194162.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
59°F 80°F 68°F 0.00 in.0.00 in.0.00 in.21%29%35%35°F 8.2 mph 12 mph 20 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
62°F
Clear
66°F
Clear
77°F
Clear
80°F
Clear
74°F
Clear
67°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:05:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:00 AM PST