HomeMy WebLinkAbout2022-02-10FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 2/10/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- We are removing the hay from the v ditch
- We are digging, detecting, and repairing leaks for the PW line
near buildings 17 and 15
- Work continues on the level spreaders
-
2 Daniel Ford No 20-HEADWORKS AREA - Work continues on the supports at the fine screens.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed
- The 6" BV cassette air, and spools area being installed.
- Instal the bolts at the PRW pumps
- Work continues for on mounting all the cassette tank and the
FRP lids is ongoing
- Supports are being installed for the WAS and The SCUM
systems
4 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The Diffusers continue to be worked on
- We connected all the SS blower piping to the diffusers on the
East side of the tank
- The FRP baffles are being bolted up
5 Daniel Ford No 60-PRODUCT WATER AREA - Placed concrete in a 4'x4' slap for the 20" overflow off the
outfall balance tank.
6 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- We removed the pancakes in the 14" line
7 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
Work continues for the diffuser install
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 10:00 AM PST
MANPOWER LOG 25 Workers | 201.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
4 J.R. Filanc Construction Company, Inc.7 8.0 56.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Daniel Waddle
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 10:00 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
25 201.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 10:00 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
53°F 82°F 65°F 0.00 in.0.00 in.0.00 in.24%38%69%38°F 3.6 mph 7 mph 13 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
62°F
Clear
65°F
Clear
77°F
Clear
79°F
Clear
62°F
Clear
55°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 08:05:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 4 of 4 Printed on 1/24/2023 at 10:00 AM PST