HomeMy WebLinkAbout2022-02-12FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Saturday 2/12/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed for the bypass air
- Instal the bolts at the PRW pumps
- Fab and install 6x5 SS spools at cassette air
- We grouted the fine screens at the MBR
- We formed the pipe bases for the WAS and Scum pump (5
places)
3 Daniel Ford No 30-TREATMENT AREA>31-
Treatment Area - BNR
Basins
- The FRP baffles are being bolted up
4 Daniel Ford No 60-PRODUCT WATER AREA - We installed 3 globe valves in this area today
-fabricated and installed the 4" sight glass.
5 Daniel Ford No 70-RESIDUALS AREA>73-
Residuals Area - SAFE Filter
System
- We removed the pancakes in the 14" line
6 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- S>S piping and diffusers are being installed.
7 Daniel Ford No 20-HEADWORKS AREA>22-
Headworks Area - Fine
Screens
- Fabricated and install S.S.Mount for the flow level switch
FBV Morro Bay Joint Venture Page 1 of 3 Printed on 1/24/2023 at 10:02 AM PST
MANPOWER LOG 9 Workers | 74.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
9 74.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 3 Printed on 1/24/2023 at 10:02 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 United Rental 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
56°F 74°F 64°F 0.00 in.0.00 in.0.00 in.31%42%62%41°F 3.6 mph 5 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
60°F
Clear
65°F
Clear
69°F
Clear
71°F
Clear
67°F
Clear
61°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 03:15:00 PM No
By Date Copies To
FBV Morro Bay Joint Venture Page 3 of 3 Printed on 1/24/2023 at 10:02 AM PST