Loading...
HomeMy WebLinkAbout2022-02-15FBV Morro Bay Joint Venture 2999 Oak Rd. #490 Walnut Creek , California 94597 Project: 471 - Morro Bay Water Reclamation Facility  Morro Bay , California 93442 Daily Log: Tuesday 2/15/2022    NOTES LOG    No.Created By Issue?Location Comments   1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed. - The fencing contractor is removing al of thier spoils from - We are digging, detecting, and repairing leaks for the PW line - We are working on the grading on the west side of the v ditch for landscape rock - Work on the level spreaders continues - Grading for fence guy - Work on the chemical vaults continues - We charged the PW- PRW lines and pressure testing continues. 2 Daniel Ford No 20-HEADWORKS AREA - We are piping for the 2 added hose bibs in the Headworks area - The supports for the Foul air are being worked on. 3 Daniel Ford No 30-TREATMENT AREA>32- Treatment Area - MBR System - The 3/4 inch SS lines are being installed for the bypass air - Instal the bolts at the PRW pumps - Work continues for on mounting all the cassette tank and the FRP lids is ongoing - Bolts are being installed everywhere in this area - Anchors and supports for the MBR are being installed 4 Daniel Ford No 60-PRODUCT WATER AREA - Anchors continue to be installed - the 3" Drain pipe at the Calcite tank continues - Globe valves are being installed 5 Daniel Ford No 70-RESIDUALS AREA>71- Residuals Area - Sludge Holding Tanks & SAFE Settle Tank Work continues for the diffuser install and for the blower piping   FBV Morro Bay Joint Venture Page 1 of 8 Printed on 1/24/2023 at 10:03 AM PST          MANPOWER LOG 37 Workers  |   304.0 Man Hours No.Contact/Company Workers # Hours Man Hours Location     1 RARIG CONSTRUCTION, INC.4 8.0 32.0 70-RESIDUALS AREA>72-Residuals Area - Dewatering Facility     Notes:Ridge cap, gutter, and gable Created By:  Michael Rarig    2 ELECTRICRAFT, INC.5 8.0 40.0     Notes:Created By:  Rick Howland   3 J.R. Filanc Construction Company, Inc.7 8.0 56.0 00-GENERAL     Notes:JOURNEYMAN LABORERS Manny Hernandez Estaban zamudio Charlie Gonzales Angel Diaz Martin Castillo Norman Gularte Daniel Waddle Created By:  Daniel Ford    4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL     Notes:LABORER APPRENTICE Jonathan Torres Alex Rios lopez Teddy Maldanado Javier Trevino Created By:  Daniel Ford    5 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL     Notes:JOURNEYMAN CARPENTERS Coy Brite Brian Elgin Rick Jenne Orlando Cortez Jason Hawthorne Created By:  Daniel Ford      FBV Morro Bay Joint Venture Page 2 of 8 Printed on 1/24/2023 at 10:03 AM PST        No.Contact/Company Workers # Hours Man Hours Location     6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:CARPENTER APPRENTICE Enrique Padilla Micha Pixley Created By:  Daniel Ford    7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:Certified Welder Pipefitter Rick Dayton Created By:  Daniel Ford    8 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL     Notes:APPRENTICE CEMENT MASON Adolfo Campoverde Created By:  Daniel Ford    9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:Operator Trevor Hernandez Kyle Brooking Created By:  Daniel Ford    10 J.R. Filanc Construction Company, Inc.1 7.0 7.0     Notes:Labor Forman Ricardo Belmontez Created By:  Daniel Ford    11 J.R. Filanc Construction Company, Inc.1 8.0 8.0     Notes:JOURNEYMAN CEMENT MASON Daniel Sheslingoff Created By:  Daniel Ford    12 Parada Painting Inc.4 10.0 40.0 70-RESIDUALS AREA>72-Residuals Area - Dewatering Facility     Notes:3 journey 1 apprentice Created By:  Monica Weiss       37  304.0    Manpower Log's Attachments:  2.  ELECTRICRAFT, INC.    FBV Morro Bay Joint Venture Page 3 of 8 Printed on 1/24/2023 at 10:03 AM PST          2-15-2022 Daily Report.xls   12.  Parada Painting Inc.  2022.02.15 Parada Painting.pdf   EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 United Rental 8.0 0.0 No   06:05AM  00-GENERAL  Notes:18000 pound mini excavator Created By: Daniel Ford   2 United Rental 8.0 No   12:20PM  00-GENERAL  Notes:Scissor lift Created By: Daniel Ford   3 AHERN RENTAL 8.0 No   05:40AM    Notes:Scissor lift Created By: Daniel Ford   4 United Rental 8.0 No   03:05PM  00-GENERAL  Notes:24k generator Created By: Daniel Ford   5 AHERN RENTAL 8.0 No   05:40AM    Notes:45' ariel lift Created By: Daniel Ford   6 United Rental 8.0 No   02:00PM  00-GENERAL  Notes:Telescoping Forklift Created By: Daniel Ford     FBV Morro Bay Joint Venture Page 4 of 8 Printed on 1/24/2023 at 10:03 AM PST          DELIVERY LOG No.Time Delivery From Tracking Number Contents   1 07:20AM   Burt industrial Supply 103547 Antisieze    Comments:Created By: Monica Weiss 2 07:20AM   Ferguson Enterprises, LLC 9746085 471-184    Comments:Created By: Monica Weiss 3 07:20AM   Ferguson Enterprises, LLC 9753619 Landscape PVC    Comments:Created By: Monica Weiss 4 07:20AM   Ferguson Enterprises, LLC Zephyr Fume Hood    Comments:Created By: Monica Weiss 5 07:20AM   PC Mechanical EQ Repair    Comments:Created By: Monica Weiss 6 07:20AM   PRW Steel 471-187 Stainless Steel Pipe and Sleeve    Comments:Created By: Monica Weiss Delivery Log's Attachments: 1.  2022.02.15 Burt Industrial 103547 Antisieze.pdf   FBV Morro Bay Joint Venture Page 5 of 8 Printed on 1/24/2023 at 10:03 AM PST        2.  2022.02.15 Ferguson 9746085 471-184.pdf 3.  2022.02.15 Ferguson 9753619 PVC S40.pdf 4.  2022.02.15 Ferguson Zephyr Hood.pdf   FBV Morro Bay Joint Venture Page 6 of 8 Printed on 1/24/2023 at 10:03 AM PST        5.  2022.02.15 PC Mechanical Repair.pdf 6.  2022.02.15 PRW Steel 471-187.pdf   WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 45°F 56°F 52°F 0.00 in.0.00 in.0.00 in.37%60%88%39°F 6.7 mph 14 mph 20 mph   DAILY SNAPSHOT 06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM Clear   48°F Clear   51°F Clear   56°F Clear   56°F Clear   52°F Clear   50°F   OBSERVED WEATHER CONDITIONS No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea   1 03:20:00 PM No     FBV Morro Bay Joint Venture Page 7 of 8 Printed on 1/24/2023 at 10:03 AM PST            By  Date  Copies To   FBV Morro Bay Joint Venture Page 8 of 8 Printed on 1/24/2023 at 10:03 AM PST