Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 2/18/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- The fencing contractor is removing al of thier spoils from
- We are digging, detecting, and repairing leaks for the PW line
- We are working on the grading on the west side of the v
ditch for landscape rock
- Work on the level spreaders continues
- Grading for fence guy
- Work on the chemical vaults continues
- pressure testing continues.
2 Daniel Ford No 20-HEADWORKS AREA - We are piping for the 2 added hose bibs in the Headworks
area
- The supports for the Foul air are being worked on.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed for the bypass air
- Instal the bolts at the PRW pumps
- Work continues for on mounting all the cassette tank and the
FRP lids is ongoing
- Bolts are being installed everywhere in this area
- Anchors and supports for the MBR are being installed
4 Daniel Ford No 60-PRODUCT WATER AREA - Anchors continue to be installed
- the 3" Drain pipe at the Calcite tank continues
- Globe valves are being installed
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
Work continues for the diffuser install and for the blower
piping
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 10:04 AM PST
MANPOWER LOG 32 Workers | 245.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Brian Elgin
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.3 8.0 24.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Enrique Padilla
Micha Pixley
Raul Velasquez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 10:04 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 Parada Painting Inc.2 2.0 4.0 70-RESIDUALS
AREA>72-Residuals
Area - Dewatering
Facility
Notes:Created By: Monica Weiss
32 245.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
2-18-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 10:04 AM PST
10. Parada Painting Inc.
2022.02.18 Parada Painting.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 10:04 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:45AM AHERN RENTALS - SANTA
MARIA
7665 Forklift
Comments:Created By: Monica Weiss
2 07:45AM Airgas 3406 Gas Rod Tube
Comments:Created By: Monica Weiss
3 07:45AM Burt Industrial Supply 103750 Pipe Taps
Comments:Created By: Monica Weiss
4 07:45AM Harrington Industrial Plastics
LLC
VSF Sch 80
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.02.18 Ahern 7665 Forklift.pdf
2.
2022.02.18 Airgas 3406 Gas Rod Tube.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 10:04 AM PST
3.
2022.02.18 Burt Ind Supply 103750 TAPS.pdf
4.
2022.02.18 Harrington VSF SCH80.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
46°F 61°F 51°F 0.00 in.0.00 in.0.00 in.46%64%84%40°F 2.7 mph 5 mph 7 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
50°F
Clear
52°F
Clear
58°F
Clear
59°F
Clear
52°F
Clear
48°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 12:20:00 PM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 10:04 AM PST