HomeMy WebLinkAbout2022-02-23FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 2/23/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- Jobsite clean up
- We are working on the curb and gutter sub grade all over
the job.
- Potholing for the PW line, repairs and testing continue
- Backfilling for the PW line continues
- Putting together the shoring boxes
- The Chemical vaults south of the chemical building are
ready for concrete at the bottom (pour is scheduled for
(Tuesday March 1)
2 Daniel Ford No 20-HEADWORKS AREA - We are piping for the 2 added hose bibs in the Headworks
area
- The supports for the Foul air are being worked on.
- The supports for the Hose bibs for the top of the head works
is being instaled.
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed for the bypass air
- Install the bolts at the PRW pumps
- Work continues for on mounting all the cassette tank and
the FRP lids is ongoing
- Bolts are being installed everywhere in this area
- Anchors and supports for the MBR are being installed
- The FRP deck is being installed
4 Daniel Ford No 60-PRODUCT WATER AREA - We fabricated and installed the 10" Steel Pipe fittings for the
IPR tanks
- Instruments are being installed at the IPR, Product water
tank, and the calcite tank
- Anchor supports for the outfall slab are being installed
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:05 AM PST
NOTES LOG
No.Created By Issue?Location Comments
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Work continues for the diffuser install and for the blower
piping (Mostly Bolt up today)
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The conveyor at the dewatering is being assembled
7 Monica Weiss No SAFETY Angel Diaz
Notes Log's Attachments:
7.
2022.02.23 Angel Diaz Incident Report.pdf
MANPOWER LOG 25 Workers | 209.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Daniel Waddle
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:05 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
2 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Micha Pixley
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 9.0 18.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Samuel Rannals
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:05 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
9 Parada Painting Inc.4 10.0 40.0
Notes:Painting 1 apprentice 3 Jrny
Created By: Monica Weiss
25 209.0
Manpower Log's Attachments:
9. Parada Painting Inc.
2022.02.23 Parada Painting.pdf 2022.02.23.1 Parada Painting.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:05 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:05AM JB DEWAR, INC 195488 Fuel
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.02.23 JB Dewar 195488.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
37°F 53°F 45°F 0.02 in.0.10 in.0.10 in.42%61%83%32°F 7.2 mph 15 mph 23 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
38°F
Clear
46°F
Clear
51°F
Clear
53°F
Clear
50°F
Clear
45°F
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:05 AM PST
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:40:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:05 AM PST