HomeMy WebLinkAbout2022-02-24FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 2/24/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- Jobsite clean up
- We are working on the curb and gutter sub grade all over the
job.
- Organizing the connex, yard, and gathering materials
- Wattles were being installed today.
- Potholing for PW line, as well testing and backfilling.
- Breakdown and building the shoring boxes
- Excavation for the tie in at the front is happening
2 Daniel Ford No 20-HEADWORKS AREA - We are working on the hose bib supports
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed for the bypass air
- The 2" prw hose bib for the Hose bib at the cassette tank is
being installed
- Work continues for on mounting all the cassette tank and the
FRP lids is ongoing
- Bolts are being installed everywhere in this area
- Anchors and supports for the MBR are being installed
- We installed the modified spool for the air cassette tank
- The instruments for the Scum tank and the RO feed were
installed
4 Daniel Ford No 60-PRODUCT WATER AREA - Work continues on the pipe supports for the calcite and and
the outfall areas
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Instruments are being installed
- Hose bib supports are being installed
FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:05 AM PST
NOTES LOG
No.Created By Issue?Location Comments
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The conveyor at the dewatering is being assembled
- The Convertor supports continue to be installed
MANPOWER LOG 28 Workers | 240.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Parada Painting Inc.4 10.0 40.0 70-RESIDUALS
AREA
Notes:Primer on Safe
Created By: Monica Weiss
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Martin Castillo
Norman Gularte
Daniel Waddle
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Rick Jenne
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:05 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
10 Parada Painting Inc.4 10.0 40.0
Notes:Painting 1 apprentice 3 Jrny
Created By: Daniel Ford
28 240.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:05 AM PST
1. Parada Painting Inc.
2022.02.24 Parada Painting.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:05 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 08:10AM Flags Unlimited Flag POle
Comments:Created By: Monica Weiss
2 08:10AM Ryan Herco 471-212 A60 SS Blind Flange
Comments:Created By: Monica Weiss
3 08:10AM Shore-Tek Inc.6852 Trench Box Spreader
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.02.24 Flags Unlimited.pdf
2.
2022.02.24 Ryan Herco 471-212 A.60.pdf
FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:05 AM PST
3.
2022.02.24 Shoretek 6852 TB Spreader.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
35°F 54°F 46°F 0.00 in.0.02 in.0.10 in.25%52%77%28°F 4.1 mph 9 mph 11 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
40°F
Clear
48°F
Clear
55°F
Clear
54°F
Clear
48°F
Clear
43°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 06:50:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:05 AM PST