HomeMy WebLinkAbout2022-02-24FBV Morro Bay Joint Venture 2999 Oak Rd. #490 Walnut Creek , California 94597 Project: 471 - Morro Bay Water Reclamation Facility  Morro Bay , California 93442 Daily Log: Thursday 2/24/2022    NOTES LOG    No.Created By Issue?Location Comments   1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed. - Organizing the connexes and the laborers yard - Jobsite clean up - We are working on the curb and gutter sub grade all over the job. - Organizing the connex, yard, and gathering materials - Wattles were being installed today. - Potholing for PW line, as well testing and backfilling. - Breakdown and building the shoring boxes - Excavation for the tie in at the front is happening 2 Daniel Ford No 20-HEADWORKS AREA - We are working on the hose bib supports 3 Daniel Ford No 30-TREATMENT AREA>32- Treatment Area - MBR System - The 3/4 inch SS lines are being installed for the bypass air - The 2" prw hose bib for the Hose bib at the cassette tank is being installed - Work continues for on mounting all the cassette tank and the FRP lids is ongoing - Bolts are being installed everywhere in this area - Anchors and supports for the MBR are being installed - We installed the modified spool for the air cassette tank - The instruments for the Scum tank and the RO feed were installed 4 Daniel Ford No 60-PRODUCT WATER AREA - Work continues on the pipe supports for the calcite and and the outfall areas 5 Daniel Ford No 70-RESIDUALS AREA>71- Residuals Area - Sludge Holding Tanks & SAFE Settle Tank - Instruments are being installed - Hose bib supports are being installed   FBV Morro Bay Joint Venture Page 1 of 6 Printed on 1/24/2023 at 10:05 AM PST          NOTES LOG    No.Created By Issue?Location Comments   6 Daniel Ford No 70-RESIDUALS AREA>72- Residuals Area - Dewatering Facility - The conveyor at the dewatering is being assembled - The Convertor supports continue to be installed   MANPOWER LOG 28 Workers  |   240.0 Man Hours No.Contact/Company Workers # Hours Man Hours Location     1 Parada Painting Inc.4 10.0 40.0 70-RESIDUALS AREA     Notes:Primer on Safe Created By:  Monica Weiss    2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL     Notes:JOURNEYMAN LABORERS Manny Hernandez Estaban zamudio Charlie Gonzales Angel Diaz Martin Castillo Norman Gularte Daniel Waddle Created By:  Daniel Ford    3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL     Notes:LABORER APPRENTICE Jonathan Torres Alex Rios lopez Teddy Maldanado Javier Trevino Created By:  Daniel Ford    4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL     Notes:JOURNEYMAN CARPENTERS Coy Brite Rick Jenne Orlando Cortez Jason Hawthorne Created By:  Daniel Ford      FBV Morro Bay Joint Venture Page 2 of 6 Printed on 1/24/2023 at 10:05 AM PST        No.Contact/Company Workers # Hours Man Hours Location     5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:CARPENTER APPRENTICE Pablo Campoverde Created By:  Daniel Ford    6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL     Notes:Certified Welder Pipefitter Rick Dayton Created By:  Daniel Ford    7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL     Notes:APPRENTICE CEMENT MASON Adolfo Campoverde Created By:  Daniel Ford    8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL     Notes:Operator Trevor Hernandez Kyle Brooking Created By:  Daniel Ford    9 J.R. Filanc Construction Company, Inc.1 7.0 7.0     Notes:Labor Forman Ricardo Belmontez Created By:  Daniel Ford    10 Parada Painting Inc.4 10.0 40.0     Notes:Painting 1 apprentice 3 Jrny Created By:  Daniel Ford       28  240.0    Manpower Log's Attachments:    FBV Morro Bay Joint Venture Page 3 of 6 Printed on 1/24/2023 at 10:05 AM PST        1.  Parada Painting Inc.  2022.02.24 Parada Painting.pdf   EQUIPMENT LOG No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location   1 United Rental 8.0 0.0 No   06:05AM  00-GENERAL  Notes:18000 pound mini excavator Created By: Daniel Ford   2 United Rental 8.0 No   12:20PM  00-GENERAL  Notes:Scissor lift Created By: Daniel Ford   3 AHERN RENTAL 8.0 No   05:40AM    Notes:Scissor lift Created By: Daniel Ford   4 United Rental 8.0 No   03:05PM  00-GENERAL  Notes:24k generator Created By: Daniel Ford   5 AHERN RENTAL 8.0 No   05:40AM    Notes:45' ariel lift Created By: Daniel Ford   6 AHERN RENTAL 8.0 No   02:00PM  00-GENERAL  Notes:Telescoping Forklift Created By: Daniel Ford     FBV Morro Bay Joint Venture Page 4 of 6 Printed on 1/24/2023 at 10:05 AM PST          DELIVERY LOG No.Time Delivery From Tracking Number Contents   1 08:10AM   Flags Unlimited Flag POle    Comments:Created By: Monica Weiss 2 08:10AM   Ryan Herco 471-212 A60 SS Blind Flange    Comments:Created By: Monica Weiss 3 08:10AM   Shore-Tek Inc.6852 Trench Box Spreader    Comments:Created By: Monica Weiss Delivery Log's Attachments: 1.  2022.02.24 Flags Unlimited.pdf 2.  2022.02.24 Ryan Herco 471-212 A.60.pdf   FBV Morro Bay Joint Venture Page 5 of 6 Printed on 1/24/2023 at 10:05 AM PST        3.  2022.02.24 Shoretek 6852 TB Spreader.pdf   WEATHER REPORT Temperature Precipitation Since Humidity Windspeed Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust 35°F 54°F 46°F 0.00 in.0.02 in.0.10 in.25%52%77%28°F 4.1 mph 9 mph 11 mph   DAILY SNAPSHOT 06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM Clear   40°F Clear   48°F Clear   55°F Clear   54°F Clear   48°F Clear   43°F   OBSERVED WEATHER CONDITIONS No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea   1 06:50:00 AM No       By  Date  Copies To   FBV Morro Bay Joint Venture Page 6 of 6 Printed on 1/24/2023 at 10:05 AM PST