HomeMy WebLinkAbout2022-02-25FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Friday 2/25/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- Jobsite clean up
- We are working on the curb and gutter sub grade all over the
job.
- Organizing the connex, yard, and gathering materials
- Wattles were being installed today.
- Potholing for PW and the PRW line, as well testing and
backfilling.
- Breakdown and building the shoring boxes
- Excavation for the tie in at the front is happening (Common
trench)
- We set the shoring box in the front area and safed off the
area.
2 Daniel Ford No 20-HEADWORKS AREA - We are working on the hose bib supports
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The 3/4 inch SS lines are being installed for the bypass air
- The 2" prw hose bib for the Hose bib at the cassette tank is
being installed
- Work continues for on mounting all the cassette tank and the
FRP lids is ongoing
- Bolts are being installed everywhere in this area
- Anchors and supports for the MBR are being installed
- We installed the modified spool for the air cassette tank
- The instruments for the Scum tank and the RO feed were
installed
4 Daniel Ford No 60-PRODUCT WATER AREA - Work continues on the pipe supports for the calcite and and
the outfall areas
FBV Morro Bay Joint Venture Page 1 of 4 Printed on 1/24/2023 at 10:05 AM PST
NOTES LOG
No.Created By Issue?Location Comments
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Instruments are being installed
- Hose bib supports are being installed
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- The conveyor at the dewatering is being assembled
- The Convertor supports continue to be installed
MANPOWER LOG 24 Workers | 200.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Parada Painting Inc.4 10.0 40.0 70-RESIDUALS
AREA
Notes:Primer on Safe
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.6 8.0 48.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Manny Hernandez
Estaban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Rick Jenne
FBV Morro Bay Joint Venture Page 2 of 4 Printed on 1/24/2023 at 10:05 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Orlando Cortez
Jason Hawthorne
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 7.0 7.0
Notes:Labor Forman
Ricardo Belmontez
Created By: Daniel Ford
24 200.0
Manpower Log's Attachments:
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 3 of 4 Printed on 1/24/2023 at 10:05 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
41°F 60°F 48°F 0.00 in.0.00 in.0.02 in.27%51%68%28°F 4.8 mph 10 mph 14 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
44°F
Clear
48°F
Clear
60°F
Clear
57°F
Clear
50°F
Clear
45°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To
FBV Morro Bay Joint Venture Page 4 of 4 Printed on 1/24/2023 at 10:05 AM PST