HomeMy WebLinkAbout2022-03-03FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 3/3/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- The Subgrade work continues
- Form removal for the headworks, and outfall areas
- We repaired the frog fence today
-All open chemical manholes were barricaded (these must
remain open for 23 days the allow the moisture to evaporate
out of the concrete for the Temaric coating)
2 Daniel Ford No 20-HEADWORKS AREA - We are working on the hose bib supports
3 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- The AA Piping work continues. It is being modified to work
with the FRP cover.
- Work continues on the 3/4 ss piping
- We modified the 6" SS Air (expansions joints)
- Flow switch for the Outfall was installed
4 Daniel Ford No 60-PRODUCT WATER AREA - Pipe support grouting continues in this area.
- Instruments continue to be installed (Saddle in the IPR line)
- We installed the 2" blind for the Outfall tank
5 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
-Layout for the exterior staircase is going on.
6 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- We are installing the polymer piping and and supports
- The 1" polymer pipe
- We are fabricating the PRW for the pump at belts
7 Daniel Ford No 90-CHEMICAL FACILITY - We are laying out and forming the chem building panels
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 10:07 AM PST
MANPOWER LOG 34 Workers | 266.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 Parada Painting Inc.4 10.0 40.0 70-RESIDUALS
AREA
Notes:Primer on Safe
Created By: Daniel Ford
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Jason Hawthorne
Orlando Cortez
Brian Elgin
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 10:07 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
12 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
13 Allied Steel Co., Inc.3 3.0 9.0
Notes:Sludge tank stair
Created By: Monica Weiss
34 266.0
Manpower Log's Attachments:
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 10:07 AM PST
1. Parada Painting Inc.
2022.03.03 Parada DFR.pdf
12. ELECTRICRAFT, INC.
3-3-2022 Daily Report.xls
13. Allied Steel Co., Inc.
2022.03.03 Allied DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 10:07 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:45PM Ferguson Enterprises, LLC 471-219 SS 90
Comments:Created By: Monica Weiss
2 03:45PM Ferguson Enterprises, LLC 471-219
Comments:Created By: Monica Weiss
3 03:45PM Miner's Ace Hardware Batteries Survey A70
Comments:Created By: Monica Weiss
4 03:45PM HD Supply White Cap 46222627 471-220 Set 3G
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.03.03 Ferguson 471-219 ss90.pdf
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 10:07 AM PST
2.
2022.03.03 Ferguson 471-219.pdf
3.
2022.03.03 Miners Battery Survey A70 Dewaer.pdf
4.
2022.03.03 White Cap 46222627 471-220 3G.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
48°F 58°F 53°F 0.00 in.0.00 in.0.00 in.55%72%84%44°F 3.6 mph 7 mph 12 mph
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 10:07 AM PST
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
48°F
Cloudy
54°F
Partly Cloudy
59°F
Partly Cloudy
56°F
Cloudy
55°F
Partly Cloudy
54°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 05:50:00 AM No
By Date Copies To