No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
-All open chemical manholes were barricaded (these must
remain open for 23 days the allow the moisture to evaporate
out of the concrete for the Temaric coating)
- Cleaning the V ditch
- Draining the water lines for site tie in and removing nuts and
bolts
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- We are bolting up the SS air piping for the cassette rank
- Work continues on the 3/4 ss piping
- The lid for the Cassette tank was put into place and aligned
with the piping.
- Flow switch for the Outfall was installed
3 Daniel Ford No 60-PRODUCT WATER AREA - Saddles for the IPR drains are being installed
- Valves for the 1/2 SS air are being installed
- The swedge lock fitting are being installed
-
4 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Exterior staircase pads continue
- V clamps for the hose bibs
- Supports for Air piping are being worked on
- We are anchoring supports at the SHT
5 Daniel Ford No 70-RESIDUALS AREA>72-
Residuals Area -
Dewatering Facility
- We are installing the polymer piping and and supports
- The 1" polymer pipe
- Work continues on the belt press
6 Daniel Ford No 90-CHEMICAL FACILITY - We are laying out and anchoring down the chem building
panels.
FBV Morro Bay Joint Venture Page 1 of 5 Printed on 1/24/2023 at 10:08 AM PST
MANPOWER LOG 31 Workers | 223.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.5 8.0 40.0
Notes:Created By: Rick Howland
2 Parada Painting Inc.4 1.5 6.0 70-RESIDUALS
AREA
Notes:Hdw & BNR piping Touch up
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Jason Hawthorne
Orlando Cortez
Brian Elgin
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
FBV Morro Bay Joint Venture Page 2 of 5 Printed on 1/24/2023 at 10:08 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
12 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
31 223.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-4-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 5 Printed on 1/24/2023 at 10:08 AM PST
2. Parada Painting Inc.
2022.03.04 Parada DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 5 Printed on 1/24/2023 at 10:08 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 03:50PM Spray Systems Nozzles
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.03.04 Spray Systems Nozzles .pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
45°F 55°F 50°F 0.00 in.0.00 in.0.00 in.58%72%87%42°F 7.0 mph 14 mph 26 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Partly Cloudy
50°F
Partly Cloudy
54°F
Cloudy
55°F
Cloudy
53°F
Clear
50°F
Clear
48°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 08:50:00 AM No