HomeMy WebLinkAbout2022-03-09FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Wednesday 3/9/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- We ae glueing 4in pipe
- Jobsite clean up
- Draining the water lines for site tie in and removing nuts and
bolts
- Subgrade work continues for Granite
- Irrigation install, backfill, and install continues
- Misc Safety items all over the site
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Fabrication and installation of pipe supports continues in this
area
3 Daniel Ford No 60-PRODUCT WATER AREA - Work continues on the anchoring of the supports
- We are installing the 1/2inch brass valves
4 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- Exterior staircase pads continue
- Placing rebar and expansion paper for the concrete stair
pads
- Fabrication and install of the unistruts is ongoing
-
5 Daniel Ford No 90-CHEMICAL FACILITY - We are laying out and anchoring down the chem building
panels.
- We are moving and cleaning all chemical totes
6 Daniel Ford No 50-RO/UV BUILDING - Work continues on the 12" RO feed line
- smaller PVC is being installed all over this building
FBV Morro Bay Joint Venture Page 1 of 7 Printed on 1/24/2023 at 10:09 AM PST
MANPOWER LOG 31 Workers | 248.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.6 8.0 48.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Jason Hawthorne
Orlando Cortez
Brian Elgin
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
FBV Morro Bay Joint Venture Page 2 of 7 Printed on 1/24/2023 at 10:09 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
12 Knecht's Plumbing & Heating, Inc.1 3.0 3.0
Notes:Bracket in ceiling
Created By: Monica Weiss
13 Parada Painting Inc.2 10.0 20.0 60-PRODUCT
WATER AREA
Notes:Finish coat
Created By: Monica Weiss
31 248.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-9-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 7 Printed on 1/24/2023 at 10:09 AM PST
12. Knecht's Plumbing & Heating, Inc.
2022.03.09 Knechts DFR.pdf
13. Parada Painting Inc.
2022.03.09 Parada DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
FBV Morro Bay Joint Venture Page 4 of 7 Printed on 1/24/2023 at 10:09 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
7 shoretech 8.0 No 11:25AM 13-WASH RACK
Notes:Trench box (oil sepperator
Created By: Daniel Ford
8 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
Created By: Daniel Ford
9 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
10 Shoretec No 11:25AM 12-SOUTH - PIPING
Notes:Trench Box (front entrance)
Created By: Daniel Ford
11 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:Bull dozer
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:25AM Capital Flow SS Fittings
Comments:Created By: Monica Weiss
2 07:25AM Miner's Ace Hardware 732211
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
FBV Morro Bay Joint Venture Page 5 of 7 Printed on 1/24/2023 at 10:09 AM PST
1.
2022.03.09 Capflo SS Fittings.pdf
2.
2022.03.09 Miners 732211 Sort Bins.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
42°F 59°F 50°F 0.00 in.0.00 in.0.00 in.61%78%90%43°F 3.0 mph 7 mph 9 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
42°F
Clear
51°F
Clear
58°F
Clear
59°F
Clear
53°F
Clear
49°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 11:15:00 AM No
FBV Morro Bay Joint Venture Page 6 of 7 Printed on 1/24/2023 at 10:09 AM PST
By Date Copies To
FBV Morro Bay Joint Venture Page 7 of 7 Printed on 1/24/2023 at 10:09 AM PST