HomeMy WebLinkAbout2022-03-10FBV Morro Bay Joint Venture
2999 Oak Rd. #490
Walnut Creek , California 94597
Project: 471 - Morro Bay Water Reclamation
Facility
Morro Bay , California 93442
Daily Log: Thursday 3/10/2022
NOTES LOG
No.Created By Issue?Location Comments
1 Daniel Ford No 00-GENERAL - Continued watering the hydro seed.
- Organizing the connexes and the laborers yard
- Jobsite clean up
- Draining the water lines for site tie in and removing nuts and
bolts
- Subgrade work continues for Granite
- Irrigation install, backfill, and install continues
- Misc Safety items all over the site
- We repaired a broken piece of the PW pipe
2 Daniel Ford No 30-TREATMENT AREA>32-
Treatment Area - MBR
System
- Fabrication and installation of pipe supports continues in this
area
3 Daniel Ford No 60-PRODUCT WATER AREA - Work continues on the anchoring of the supports
- We are grouting supports at the IPR
4 Daniel Ford No 70-RESIDUALS AREA>71-
Residuals Area - Sludge
Holding Tanks & SAFE
Settle Tank
- We placed and finished the 3 pads and all footings for the
external footing on the westside.
5 Daniel Ford No 90-CHEMICAL FACILITY - We are laying out and anchoring down the chem building
panels.
- We are moving and cleaning all chemical totes
6 Daniel Ford No 50-RO/UV BUILDING - Work continues on the 12" RO feed line
- smaller PVC is being installed all over this building
FBV Morro Bay Joint Venture Page 1 of 9 Printed on 1/24/2023 at 10:09 AM PST
MANPOWER LOG 28 Workers | 212.0 Man Hours
No.Contact/Company Workers #
Hours
Man
Hours
Location
1 ELECTRICRAFT, INC.4 8.0 32.0
Notes:Created By: Rick Howland
2 J.R. Filanc Construction Company, Inc.5 8.0 40.0 00-GENERAL
Notes:JOURNEYMAN LABORERS
Esteban zamudio
Charlie Gonzales
Angel Diaz
Norman Gularte
Daniel Waddle
Manny Hernandez
Created By: Daniel Ford
3 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:LABORER APPRENTICE
Jonathan Torres
Alex Rios lopez
Teddy Maldanado
Javier Trevino
Created By: Daniel Ford
4 J.R. Filanc Construction Company, Inc.4 8.0 32.0 00-GENERAL
Notes:JOURNEYMAN CARPENTERS
Coy Brite
Jason Hawthorne
Orlando Cortez
Brian Elgin
Created By: Daniel Ford
5 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:CARPENTER APPRENTICE
Pablo Campoverde
Enrique Padilla
Created By: Daniel Ford
6 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Certified Welder Pipefitter
Rick Dayton
FBV Morro Bay Joint Venture Page 2 of 9 Printed on 1/24/2023 at 10:09 AM PST
No.Contact/Company Workers #
Hours
Man
Hours
Location
Created By: Daniel Ford
7 J.R. Filanc Construction Company, Inc.1 9.0 9.0 00-GENERAL
Notes:APPRENTICE CEMENT MASON
Adolfo Campoverde
Created By: Daniel Ford
8 J.R. Filanc Construction Company, Inc.2 8.0 16.0 00-GENERAL
Notes:Operator
Trevor Hernandez
Kyle Brooking
Created By: Daniel Ford
9 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Cement Mason
Daniel Sheslingoff
Created By: Daniel Ford
10 J.R. Filanc Construction Company, Inc.1 8.0 8.0 00-GENERAL
Notes:Labor Foreman
Ricardo Belmontes
Created By: Daniel Ford
11 J.R. Filanc Construction Company, Inc.1 8.0 8.0
Notes:Carpenter Foreman
Phil Lacey
Created By: Daniel Ford
12 Parada Painting Inc.2 1.5 3.0 20-HEADWORKS
AREA
Notes:Housekeeping
Created By: Monica Weiss
28 212.0
Manpower Log's Attachments:
1. ELECTRICRAFT, INC.
3-10-2022 Daily Report.xls
FBV Morro Bay Joint Venture Page 3 of 9 Printed on 1/24/2023 at 10:09 AM PST
12. Parada Painting Inc.
2022.03.10 Parada DFR.pdf
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
1 United Rental 8.0 0.0 No 06:05AM 00-GENERAL
Notes:18000 pound mini excavator
Created By: Daniel Ford
2 United Rental 8.0 No 12:20PM 00-GENERAL
Notes:Scissor lift
Created By: Daniel Ford
3 AHERN RENTAL 8.0 No 05:40AM
Notes:Scissor lift
Created By: Daniel Ford
4 United Rental 8.0 No 03:05PM 00-GENERAL
Notes:24k generator
Created By: Daniel Ford
5 AHERN RENTAL 8.0 No 05:40AM
Notes:45' ariel lift
Created By: Daniel Ford
6 AHERN RENTAL 8.0 No 02:00PM 00-GENERAL
Notes:Telescoping Forklift
Created By: Daniel Ford
7 shoretech 8.0 No 11:25AM 13-WASH RACK
Notes:Trench box (oil sepperator
Created By: Daniel Ford
8 AHERN RENTAL 8.0 No 11:25AM 00-GENERAL
Notes:Skid steer
FBV Morro Bay Joint Venture Page 4 of 9 Printed on 1/24/2023 at 10:09 AM PST
EQUIPMENT LOG
No.Equipment Name Cost Code Hrs Operating Hrs Idle Inspected?Inspection Time Location
Created By: Daniel Ford
9 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:loader
Created By: Daniel Ford
10 Shoretec No 11:25AM 12-SOUTH - PIPING
Notes:Trench Box (front entrance)
Created By: Daniel Ford
11 United Rental 8.0 No 11:25AM 00-GENERAL
Notes:Bull dozer
Created By: Daniel Ford
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
1 07:40AM CalPortland 1737457 Eq pads Landing
Comments:Created By: Monica Weiss
2 07:40AM Capital Flow Wedge Anchor strut
Comments:Created By: Monica Weiss
3 07:40AM Certex Rigging 2348-00
Comments:Created By: Monica Weiss
4 07:40AM Ferguson Enterprises, LLC 4in service saddle
Comments:Created By: Monica Weiss
5 07:40AM Ferguson Enterprises, LLC PVC Saddles 471-223
Comments:Created By: Monica Weiss
6 07:40AM Miner's Ace Hardware 175330 Hole Saw Bits
Comments:Created By: Monica Weiss
7 07:40AM Miner's Ace Hardware 732224 Consumables
Comments:Created By: Monica Weiss
8 07:40AM PRW Steel 471-224 S256598
Comments:Tie in header
Created By: Monica Weiss
FBV Morro Bay Joint Venture Page 5 of 9 Printed on 1/24/2023 at 10:09 AM PST
DELIVERY LOG
No.Time Delivery From Tracking Number Contents
9 07:40AM HD Supply White Cap 463220008 Safety
Comments:Created By: Monica Weiss
Delivery Log's Attachments:
1.
2022.03.10 Calportland 1737457 Eq Pads Landing.pdf
2.
2022.03.10 Capflo Wedge Anchor Strut A70.pdf
FBV Morro Bay Joint Venture Page 6 of 9 Printed on 1/24/2023 at 10:09 AM PST
3.
2022.03.10 Certex Rigging 2348-00.pdf
4.
2022.03.10 Ferguson 4in Service Saddle Inj.pdf
5.
2022.03.10 Ferguson PVC Saddles 471-223.pdf
FBV Morro Bay Joint Venture Page 7 of 9 Printed on 1/24/2023 at 10:09 AM PST
6.
2022.03.10 Miners 175330 Hole Saw Bits.pdf
7.
2022.03.10 Miners Supplies 732224.pdf
8.
2022.03.10 PRW Steel 471-224 S256598.pdf
FBV Morro Bay Joint Venture Page 8 of 9 Printed on 1/24/2023 at 10:09 AM PST
9.
2022.03.10 White Cap 46322008 Safety.pdf
WEATHER REPORT
Temperature Precipitation Since Humidity Windspeed
Low High Avg Midnight 2 Days Ago 3 Days Ago Low Avg High Dew Avg Max Gust
43°F 58°F 52°F 0.00 in.0.00 in.0.00 in.28%69%89%41°F 5.4 mph 7 mph 12 mph
DAILY SNAPSHOT
06:00AM 09:00AM 12:00PM 03:00PM 06:00PM 09:00PM
Clear
45°F
Clear
54°F
Clear
57°F
Clear
57°F
Clear
55°F
Clear
58°F
OBSERVED WEATHER CONDITIONS
No.Time Observed Weather Delay Sky Temp Average Precipitation Wind Ground/Sea
1 07:10:00 AM No
By Date Copies To